Dear All,
Below please find the minutes from our meeting on August 4th.
Greetings,
Bill

Minutes from the eRHIC IR Design meeting held on August 4, 2017
---------------------------------------------------------------------------------------
Agenda:
- Bob's Presentation
- Update on effort to match IR to the rest of the Lattice
- Geometry Update
* Bob's Presentation:
- presents argument why for ring-ring design one expects (possible?) epsilon_y_e << epsilon_x_e
- makes point that with short, flat beams that one may be able to operate without crab cavities and lose only ~40% of the luminosity.
- brief discussion of whether it could be possible to operate without a crossing angle, difficult is one wants a small beta*.
- Bob explains the choices of divergences, essentially balancing luminosity vs acceptance and measurement errors.
- Elke emphasizes the point again that the possibility of running with small divergences in both directions (x & y) will be an important feature (choice #3 in Bob's list). Important for the p-e physics program.
- Elke makes the point that the divergence of the Au beam is important as well, as it ties into the neutron acceptance. As important as the proton divergence is in p-e.
- Bob presents slide defining three levels of cooling
- Conclusion on cooling discussion, it gets down to how one wants to present it
- Moderate cooling with CeC:
- If CeC works then all good
- If CeC doesn't work, assess different cooling techniques
End of Bob's presentation
* Matching IR to rest of Lattice Update
- One meeting has been held
- Homework was assigned and done
- Discussions at meeting
- Parameters to use (language)
- Which things to work on first
- An ongoing effort
* Geometry Update
- Bill had talked with Ferdi about desire to have the geometry for the IR put into a drawing
- Ferdi commented that too early to get designers involved, to involve them one needs precise numbers, inefficient at this point
- Idea to try and draw up preliminary geometry drawings with simpler software packages
- Suggestion to speck with Dejan about possibly getting Stephen involved in this

* Discussion of next meeting
- Schedule for two weeks from today (i.e. next mtg on August 18th at 2 pm)
- Cancel if deemed desirable
- Update on geometry
- update on the lattice matching effort.
End of Meeting