Dear Colleagues
I'm sending you the request for the rough plan of beam tests. We should discuss it ASAP and let them know. Please have a look:
---------- Forwarded message ---------
Od: Friederike Bock <friederike.bock AT cern.ch>
Date: czw., 7 lis 2024 o 11:28
Subject: Re: Testbeam plans for ePIC LFHCAL in the next ~year?
To: Novitzky, Norbert <novitzkyn AT ornl.gov>, Hartbrich, Oskar <hartbricho AT ornl.gov>, miguel.arratia AT ucr.edu <miguel.arratia AT ucr.edu>, Leszek.kosarzewski AT gmail.com <leszek.kosarzewski AT gmail.com>, Brandenburg, Daniel <brandenburg.89 AT osu.edu>, Stefan Bathe <stefan.bathe AT baruch.cuny.edu>, Megan Connors <meganeconnors AT gmail.com>
Cc: prakhar.garg AT yale.edu <prakhar.garg AT yale.edu>
Od: Friederike Bock <friederike.bock AT cern.ch>
Date: czw., 7 lis 2024 o 11:28
Subject: Re: Testbeam plans for ePIC LFHCAL in the next ~year?
To: Novitzky, Norbert <novitzkyn AT ornl.gov>, Hartbrich, Oskar <hartbricho AT ornl.gov>, miguel.arratia AT ucr.edu <miguel.arratia AT ucr.edu>, Leszek.kosarzewski AT gmail.com <leszek.kosarzewski AT gmail.com>, Brandenburg, Daniel <brandenburg.89 AT osu.edu>, Stefan Bathe <stefan.bathe AT baruch.cuny.edu>, Megan Connors <meganeconnors AT gmail.com>
Cc: prakhar.garg AT yale.edu <prakhar.garg AT yale.edu>
Hi Oskar,
LFHCal request 1 week of TB at PS and SPS between Sept 1st and Nov 1st
and would in principle open to have a parasite ;).
Regards,
Fredi
On 11/7/24 11:00, Novitzky, Norbert wrote:
> Hi Oskar,
>
> I know the FoCal one at CERN:
> wk 33 - 34 ; 37 - 40 PS T9
> wk 1 - 27 :: PS T9
> wk 31 - 34 :: SPS H2
> wk 37 - 40 :: SPS H2
> wk 38 - 48 :: SPS H2
> The PS is mostly PADs which I am not part of, the H2 ones will be a full prototype test E+HCals (pointing out that it will be probably too full to include a parasitic detector).
>
> I know barrel HCal is planning a testbeam at Fermilab, but that is now a big question mark. As far as I know it will be ready by spring time, but not sure ‘where’ can it be tested – the prototype is quite large and heavy (15t) for easy moving/shipping. But I included Stephan and Megan also.
>
> Best,
> Norbert
>
> From: Hartbrich, Oskar <hartbricho AT ornl.gov>
> Date: Wednesday, November 6, 2024 at 1:06 PM
> To: Friederike Bock <Friederike.Bock AT cern.ch>, miguel.arratia AT ucr.edu <miguel.arratia AT ucr.edu>, Novitzky, Norbert <novitzkyn AT ornl.gov>, Leszek.kosarzewski AT gmail.com <leszek.kosarzewski AT gmail.com>, Brandenburg, Daniel <brandenburg.89 AT osu.edu>
> Cc: prakhar.garg AT yale.edu <prakhar.garg AT yale.edu>
> Subject: Testbeam plans for ePIC LFHCAL in the next ~year?
> Dear Fredi, Miguel, Norbert, Leszek and Dan,
> We are trying to compile an overview of plans for beam tests of ePIC sub-systems in the coming year or so, including beam times that might not be ePIC specific, but still aligned with the LFHCAL program. (I’m thinking of backward HCAL beam times using LFHCAL infrastructure, ALICE FOCAL testbeams using Norbert’s HGCROC developments etc.)
>
> Ideally I would like to present that overview already at the next TIC meeting this coming Monday.
>
> Could you give me a summary of such plans along the lines of “when and how much beam time” (roughly), “where” and “what is to be tested” (roughly)? That would be immensely helpful! (In the LFHCAL case I have the CERN beamtime application already, of course 😉)
>
> Cheers,
> Prakhar and Oskar for the TC-office
--
Dr. Friederike Bock
Staff scientist
Oak Ridge National Laboratory, P.O. Box 2008., Oak Ridge, TN 37831
mobile: +1 865 308 7900
office: 6000/R-220
- [[Epic-backward-hcal-l] ] Fwd: Testbeam plans for ePIC LFHCAL in the next ~year?, Leszek Kosarzewski, 11/08/2024
Archive powered by MHonArc 2.6.24.