Folks-
There is no meeting this week, next one in 3 weeks, but I wanted
to update everyone on a number of issues:
- I have gotten an unoffical response from Hamamatsu that the
first SiPM delivery will be for 8.5K devices in late February of
2019. I read that as a receipt of devices at BNL on
1-March-2019. We should be able to get them to UofM within a
week of that for testing. We should start to think ab out
testing starting on or about 15-Mar-2019. As usual, all dates
are subject to change.
- EMCal Sector 0 preamps have been received, we are working on
Q/A testing.
- EMCal Sector 0 SiPM daughter board order is out (almost). 8
week turn with holiday disruptions.
- EMCal Sector 0 Interface Board order is being processed, 6-8
week turn.
- Paperwork for HCal Modules 1-6 electronics orders is being put
together. Test boards are being assembled for a test fit in the
Module 1 steel to verify mechanical issues
- 7-Crate Digitizer order paper work has been submitted and
starting to work it's way through the paper mill. There will be
a review of the digitizer system in mid December. John H's
white board has a tentative date of Dec 13 for the review.
I will be out of office with limited e-mail access 9-25 Nov.
See you in Tallahassee Dec 6.
Eric
--
Eric J. Mannel, Ph.D.
sPHENIX Group
Physics Dept.
Brookhaven National Laboratory
631/344-7626 (Office)
914/659-3235 (Cell)
|
-
[Sphenix-electronics-l] SiPM order Update,
Eric Mannel, 11/05/2018
Archive powered by MHonArc 2.6.24.