Hi Sean and All,
  That's absolutely fantastic news ! Congratulations to you and all the EMCAL team and the fabulous crew in 1008 for making this possible and getting it done. It's truly a milestone for sPHENIX. Many thanks to everyone who worked on this and enjoy a very Happy Thanksgiving !

Cheers,
Craig

On 11/23/2022 3:55 PM, Stoll, Sean wrote:

All,

With a notable effort over the weeks following magnet mapping, the 1008 Crew installed the final sector-pair into the magnet this afternoon. Thanks to all for your hard work.  Enjoy a well-earned break with family and friends.

 

Sean


_______________________________________________
sPHENIX-EMCal-l mailing list
sPHENIX-EMCal-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-emcal-l




Archive powered by MHonArc 2.6.24.

Top of Page