Skip to Content.
Sympa Menu

sphenix-hcal-l - Re: [Sphenix-hcal-l] Fwd: Transformer failure at Fermilab damages power supply for Recycler

sphenix-hcal-l AT lists.bnl.gov

Subject: sPHENIX HCal discussion

List archive

Chronological Thread  
  • From: Abhisek Sen <sen.abhisek AT gmail.com>
  • To: eric mannel <mannel AT bnl.gov>
  • Cc: sphenix-emcal-l AT lists.bnl.gov, sphenix-hcal-l AT lists.bnl.gov
  • Subject: Re: [Sphenix-hcal-l] Fwd: Transformer failure at Fermilab damages power supply for Recycler
  • Date: Sat, 23 Apr 2016 22:59:20 -0500

Beam is back now.

Cheers,
Abhisek

On Sat, Apr 23, 2016 at 5:05 PM, eric mannel <mannel AT bnl.gov> wrote:
Best estimate for beam according to MCR is some time later tonight.......


-------- Forwarded Message --------
Subject: Transformer failure at Fermilab damages power supply for Recycler
Date: Sat, 23 Apr 2016 21:54:29 +0000
From: Fermilab News <news AT fnal.gov>
To: allhands <allhands AT fnal.gov>, all-users <all-users AT fnal.gov>


On Saturday, April 23, 2016, at about 1:15 p.m., a transformer located on the Fermilab site at MI-60 malfunctioned and resulted in a fire. Fire companies from Fermilab, Batavia, Geneva, and North Aurora responded and extinguished the fire. Nobody was injured.

 

The fire, started by the malfunctioning transformer, damaged a power-supply system that is critical to the operation of the Recycler storage ring of the Fermilab accelerator complex.  Experts are still making detailed assessments about when the Main Injector would restart, likely operating at lower intensities without the Recycler. 

 

Preliminary investigations indicate that mineral oil located inside the transformer at MI-60 fueled the fire. The fire damaged an adjacent utility building and the power supply located inside that building. The plume of smoke may have been visible off site.

 

Fermilab will provide an update in the next few days when more information about the needed repairs is available.

 

Tim Meyer, Fermilab Chief Operating Officer


-- 
Eric J. Mannel, Ph.D.
PHENIX Group
Physics Dept.
Brookhaven National Laboratory
631/344-7626 (Office)
914/659-3235 (Cell)



_______________________________________________
Sphenix-hcal-l mailing list
Sphenix-hcal-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-hcal-l





Archive powered by MHonArc 2.6.24.

Top of Page