sphenix-hcal-l AT lists.bnl.gov
Subject: sPHENIX HCal discussion
List archive
- From: John Lajoie <lajoie AT iastate.edu>
- To: sphenix-hcal-l AT lists.bnl.gov
- Subject: Re: [Sphenix-hcal-l] Single layer IHC for sPHENIX
- Date: Mon, 11 Sep 2017 13:02:33 -0500
Hi Edward, Thanks for sending out a drawing of what you proposed at the
general meeting on Friday - it's very helpful. I think the mechanical structure you are proposing could be a
very straightforward evolution of what we have now (in steel). If
you built the existing structure (with small mods for the
scintillator) and just instrumented it with scintillator on the
back it could cost a little less because you don't have to worry
about the mechanical tolerances of the gaps, but by definition it
would (a) be able to hold the weight of the EMCal, and (b) have
the same amount of absorber as it does now. Still, this
iteration is likely going to be a little more than $1M for the
mechanical structure - it's still a lot of stainless steel. You can gain some additional savings by making the plates
thicker, that will reduce machining. If you reduced the radial
size of the steel so that it was about half an interaction length
- which gets me to what I think that's what you are proposing in
your slides - you certainly won't cut the remaining cost in half,
as most of the cost is in machining. Of course, then you will
still need to make sure that the reduced structure is stiff enough
to hold the EMCal, but it is probably OK if the thickness of the
plates is increased by a factor of two. There would be some additional savings on the scintillator
and electronics, since we are reducing the number of channels by
four, but you would still need to pay to have them assembled,
shipped, etc. My offhand feeling, from working with the BoE's and
RLS for some time, is that you would overall save less than a
million (before contingency), but that could be worked out in more
detail. Not chump change, but not a large bite out of the larger
problem. I think we would want to try, as much as possible, to use the
existing calorimeter readout scheme for the tiles. Anything else
is an R&D project that I don't think we would have time for. I'll have a talk with our machinists that build the current
prototype to see if they can give use some back-of-the envelope
numbers for potential cost savings with this kind of a structure.
Without a detailed design it might be difficult but they might be
able to estimate it as deltas from the current design (as I did
above). Regards, On 9/11/2017 10:00 AM, Edouard Kistenev
wrote:
_______________________________________________ sPHENIX-HCal-l mailing list sPHENIX-HCal-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/sphenix-hcal-l --
Contact me: john.lajoie |
-
[Sphenix-hcal-l] Single layer IHC for sPHENIX,
Edouard Kistenev, 09/11/2017
-
Re: [Sphenix-hcal-l] Single layer IHC for sPHENIX,
John Lajoie, 09/11/2017
- Re: [Sphenix-hcal-l] Single layer IHC for sPHENIX, Edouard Kistenev, 09/11/2017
-
Re: [Sphenix-hcal-l] Single layer IHC for sPHENIX,
John Lajoie, 09/11/2017
Archive powered by MHonArc 2.6.24.