Dear Stefan,
The 6th shipment (> 1000 tiles) arrived at ATL this morning. It may take a
couple of days to pass through the custom before it is delivered to GSU.
My understanding is that all of the remaining plastic components are included
in this shipment. Once we get them, they will be shipped to BNL in a
following pallet(s).
Cheers,
Xiaochun
--
On 8/11/20, 1:53 PM, "sPHENIX-HCal-l on behalf of Stefan Bathe"
<sphenix-hcal-l-bounces AT lists.bnl.gov on behalf of bathe AT bnl.gov> wrote:
Hello,
In yesterday’s engineering meeting the question came up how many salt
shakers (LED cups) and fiber plugs we have in the tent.
We have 3 sectors installed (cups and plugs) and 1 additional sector
ready to install (cups and plugs); that’s 4 sectors.
Then we have 10 additional fiber plugs in the tent (so 1 sector worth of
plugs).
Finally we have 100 cup/plug sets (so 10 sectors worth of).
So it looks like we have cup/plug sets for 10 production sectors in
addition to the 6 preproduction sectors (assuming the cups/plugs for the 2/1
missing preproduction sectors are floating around in Sal’s lab somewhere).
That means we need cups/plugs for 16 more sectors from Uniplast.—Is that
correct, Edward? (Or maybe they are at GSU already?)
Regards,
Stefan
_______________________________________________
sPHENIX-HCal-l mailing list
sPHENIX-HCal-l AT lists.bnl.gov
https://urldefense.com/v3/__https://nam03.safelinks.protection.outlook.com/?url=https*3A*2F*2Flists.bnl.gov*2Fmailman*2Flistinfo*2Fsphenix-hcal-l&data=02*7C01*7Cxhe*40gsu.edu*7C8be32ae6b25345a8827808d83e1f6ca2*7C515ad73d8d5e4169895c9789dc742a70*7C0*7C0*7C637327651976257164&sdata=m5GcGjcZxd0RkQBziNv4C98z2h4Iqel4K8bqGhWmC*2Fg*3D&reserved=0__;JSUlJSUlJSUlJSUlJSUlJQ!!P4SdNyxKAPE!SWsOx8g77k74y1Zy1VVVlHVxQEKe7lRL4BVNr3oDP-B13N7Q1GsXV5E5KRFi4G7k8Znh0Q6UB90$
-
[Sphenix-hcal-l] Follow-up on yesterday's engineering meeting: salt shaker inventory,
Stefan Bathe, 08/11/2020
-
Re: [Sphenix-hcal-l] Follow-up on yesterday's engineering meeting: salt shaker inventory,
Xiaochun He, 08/11/2020
- Re: [Sphenix-hcal-l] Follow-up on yesterday's engineering meeting: salt shaker inventory, Stefan Bathe, 08/11/2020
-
Re: [Sphenix-hcal-l] Follow-up on yesterday's engineering meeting: salt shaker inventory,
Xiaochun He, 08/11/2020
Archive powered by MHonArc 2.6.24.