sphenix-hcal-l AT lists.bnl.gov
Subject: sPHENIX HCal discussion
List archive
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control
- From: Stefan Bathe <stefan.bathe AT baruch.cuny.edu>
- To: "Boose, Stephen" <boose AT bnl.gov>
- Cc: Stefan Bathe <bathe AT bnl.gov>, "sphenix-hcal-l AT lists.bnl.gov" <sphenix-hcal-l AT lists.bnl.gov>, "Miraglia, Damon" <dmiraglia AT bnl.gov>, John Haggerty <haggerty AT bnl.gov>, Eric Mannel <mannel AT bnl.gov>, Rosi Reed <rosijreed AT lehigh.edu>
- Subject: Re: [Sphenix-hcal-l] ADC Crate Remote Power Control
- Date: Tue, 12 Mar 2024 15:22:54 -0400
Hi Steve,
Thanks!
Essentially anytime that is convenient for you. Just check in with the shift crew to make sure that there is nothing special going on. If it’s just the default cosmics data taking, they can interrupt that for an hour, no problem. (I confirmed that with Jamie.)
Would you like to schedule this for a particular time? Then we could just request that at the shift change meeting the day before.
Best regards,
Stefan
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
On Mar 11, 2024, at 11:31, Boose, Stephen <boose AT bnl.gov> wrote:* This email originates from a sender outside of CUNY. Verify the sender before replying or clicking on links and attachments. *
<backendGUI.png>Hi Stefan,We have this remote ADC crate power control GUI in place which can be used by experts in such rare cases that a crate may need to be power cycled from outside the IR without killing the whole rack. This morning I finished testing the EmCAL and sEPD portion – tested OK.To finish the HCal portion we would need an opportunity at the HCal group’s convenience to have Damon shut down 2E2 and connect the MegaPAC control cable there. This could take an hour or so because it requires moving some cables. Then I’d be able to test both 2E2 and 2W2.So please let us know of a convenient time for this interruption – no rush JMany thanks,Steve BoosePrincipal Electrical EngineersPHENIX ExperimentBrookhaven National LaboratoryBLDG 510CUpton, NY 11973Office: 631 344-2897
-
[Sphenix-hcal-l] ADC Crate Remote Power Control,
Boose, Stephen, 03/11/2024
-
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control,
Rosi Reed, 03/11/2024
-
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control,
Boose, Stephen, 03/11/2024
- Re: [Sphenix-hcal-l] ADC Crate Remote Power Control, Anderson, Derek [PHYSA], 03/11/2024
-
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control,
Boose, Stephen, 03/11/2024
-
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control,
Stefan Bathe, 03/12/2024
- Re: [Sphenix-hcal-l] ADC Crate Remote Power Control, Boose, Stephen, 03/13/2024
-
Re: [Sphenix-hcal-l] ADC Crate Remote Power Control,
Rosi Reed, 03/11/2024
Archive powered by MHonArc 2.6.24.