sphenix-l AT lists.bnl.gov
Subject: sPHENIX is a new detector at RHIC.
List archive
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion
- From: EdwardOBrien <eobrien AT bnl.gov>
- To: sphenix-l AT lists.bnl.gov
- Subject: Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion
- Date: Wed, 27 Apr 2016 14:09:18 -0400
Dear Gunther, I have a very strong opinion on the issue of the baseline detector. The Project team has been telling Berndt for months that the sPHENIX baseline design is a the EMCal and HCal as specified in the pCDR plus the reused pixels and compact TPC. Why? Because the project has been given a very strict guideline on total cost. The TPC cost including manpower that we'd have to pay for has been looked at carefully and we believe that this is the cheapest option by far unless there is outside money, such as JSPS money, to build something else. If the collaboration wants to propose that the baseline is changed to 5-6 layers of MAPS as the Tracker then you better bring that to Berndt before you do anything. Unfortunately, it won't pass the laugh test. On cost alone the 7 layer ALICE ITS is estimated at $30M with a low contingency and standard US accounting. In addition the November Cost and Schedule review committee concluded that cost aside, the collaboration had neither the schedule nor expertise to pull off a MAPS pixel detector. Despite the hard work of one person at LANL there has been little progress on the MAPS option since November beyond his effort. I'd also like to point out that nothing beyond the inner 3 layers of the ITS was discussed in the plenary session of the Santa Fe workshop. Now some are proposing 5 layers minimum. Here is my proposal: 1) Agree that whatever Tracker solution we adopt will be cost neutral, i.e $5M AY in material cost + 40% contingency. That is what we should tell Berndt. Whatever solution we choose will be cost neutral. 2) Independently complete that Cost and Schedule exercise on MAPS that was started at the Santa Fe workshop. Mike McCumber has started on it. We have a standard approach to this that has been applied to all the subsystems, except the si strip Tracker option, and it needs to be applied to MAPS. 3) Recommend a cost reduction of $4-4.5M plus contingency and simulate that before the May deadline. These 3 suggestions imply that no reduction will be taken from the $5M set aside for the Tracker. I suggest that you and I run this by Berndt before we go to a lot of effort and find that he wants something else. Thanks. Ed On 4/27/2016 11:31 AM, Gunther M Roland
wrote:
Hi John,
Thanks for your comments, and thanks for being frank! We
should make the decision very soon (24h?). I hope more people
will weigh in shortly. We are talking to the simulations gurus
to make sure that we don't decide on a reference configuration
that we are not actually ready to simulate right away.
Gunther
_______________________________________________ Sphenix-l mailing list Sphenix-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/sphenix-l |
-
[Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Gunther M Roland, 04/26/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Lajoie, John G [PHYSA], 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Gunther M Roland, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
EdwardOBrien, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Lajoie, John G [PHYSA], 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Frawley, Anthony, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
EdwardOBrien, 04/27/2016
- Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion, Frawley, Anthony, 04/27/2016
- Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion, Gunther M Roland, 04/27/2016
- Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion, EdwardOBrien, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
EdwardOBrien, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Frawley, Anthony, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Gunther M Roland, 04/27/2016
- Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion, Michael P. McCumber, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Lajoie, John G [PHYSA], 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
EdwardOBrien, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Gunther M Roland, 04/27/2016
-
Re: [Sphenix-l] [Response to ADL charge] Continuing detector scenario discussion,
Lajoie, John G [PHYSA], 04/27/2016
Archive powered by MHonArc 2.6.24.