  • To: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>, "haggerty AT bnl.gov" <haggerty AT bnl.gov>, David Morrison <dave AT bnl.gov>, Edward Kistenev <kistenev AT bnl.gov>, Craig Woody <woody AT bnl.gov>, Glenn Young <glennyoung82251 AT gmail.com>, "Martin L. Purschke" <purschke AT bnl.gov>, "Pontieri, Chris" <cpontieri AT bnl.gov>, Chris Pinkenburg <pinkenburg AT bnl.gov>, Mickey Chiu <chiu AT bnl.gov>, nouicer <rachid.nouicer AT bnl.gov>, Takao Sakaguchi <takao AT bnl.gov>, "Huang, Jin" <jhuang AT bnl.gov>, "Vasquez, Joel" <jvasquez AT bnl.gov>, Dan Cacace <dcacace AT bnl.gov>, "mills, James A" <mills AT bnl.gov>, "Boose, Stephen" <boose AT bnl.gov>, Bob Azmoun <azmoun AT bnl.gov>, "Pisani, Robert" <pisani AT bnl.gov>, "rfeder AT bnl.gov" <rfeder AT bnl.gov>, eric mannel <mannel AT bnl.gov>, Sean Stoll <stoll AT bnl.gov>, Richard Ruggiero <ruggiero AT bnl.gov>, Carter Biggs <biggs AT bnl.gov>, "La Bounty, James" <labounty AT bnl.gov>, "Lenz, Michael D" <mlenz AT bnl.gov>, Mariette Faulkner <faulkner AT bnl.gov>, Aaron Allen <allena AT bnl.gov>, Bill Lenz <wlenz AT bnl.gov>, Sal Polizzo <sapolizzo AT bnl.gov>, Frank Toldo <fatoldo AT bnl.gov>, Al Borrelli <borrelli AT bnl.gov>, "Hamblen, Peter (CONTR)" <phamblen AT bnl.gov>, shana Prifte <sprifte AT bnl.gov>, Chris Cordovano <ccordovan AT bnl.gov>, "Scheblein, John A" <schebs AT bnl.gov>, Timothy Rinn <timothytrinn AT gmail.com>, ejiro Umaka <eumaka AT iastate.edu>, Ejiro Umaka <eumaka1 AT bnl.gov>, "iri >> Sourikova,Irina V" <irina AT bnl.gov>
  • Subject: [Sphenix-l] Helium begins to flow in 1008 Monday October 3
  • Date: Tue, 27 Sep 2022 15:14:21 -0400

    Dear all,
     We will begin the helium flow through the 1008 cryogenic
    system on Monday October 3. The helium will flow for approximately
    two months while we exercise the magnet and map it. Once the
    helium flow starts both
the 1008 IR and Assembly Hall requires
    that one have BNL ODH
training before you enter the IR or Assembly Hall.
    The BNL ODH course can be taken online.
    Find the ODH training link on this page:
    https://www.bnl.gov/training/courses/web/

    The beginning of helium flow through the sPHENIX magnet is an
    important milestone for the installation of the detector and preparation
    for data-taking.
    Let me know if you have any questions. Thanks.

     Ed

   
   