sphenix-l AT lists.bnl.gov
Subject: sPHENIX is a new detector at RHIC.
List archive
[Sphenix-l] after approval ---> 8 am on May 19 to adjust nitrogen flow meter in IR and start to cool down the sPHENIX magnet
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>
- Cc: "sphenix-run-l AT lists.bnl.gov" <sphenix-run-l AT lists.bnl.gov>
- Subject: [Sphenix-l] after approval ---> 8 am on May 19 to adjust nitrogen flow meter in IR and start to cool down the sPHENIX magnet
- Date: Thu, 18 May 2023 22:18:47 +0000
Hi, It's good that this morning, we already talked with the C-AD Cryo group, our gas expert Rob Pisani, and Paul Sampson (C-AD maintenance/operation coordinator) in preparation for the arrival of this approval (email below --- without the original letter).
The Cryo group actually needs to open a few valves before they can cool down our Magnet and one of the valves is on the RHIC berm behind Bldg. 1008B inside the fence which is locked. That's, they also need "no beam" in order to open that valve (with some
additional works). After this approval message, I have confirmed with them and we agreed on the time of 8 am tomorrow(May 19) for the "access" (no beam). So, Rob and our technicians can adjust nitrogen flow meters inside the 1008-IR. ( A few more sPHENIX colleagues will
also go inside the IR. ) In fact, as Rob reminded me, I've checked with M. Sardzinski (C-AD Cryo group) to make sure that the LN2 dewar on the 1008 gas pad is operational tomorrow at 8 am.
Rob told me this afternoon that he'll try to flow the operational gas to TPOT as well tomorrow as TPOT has relatively smaller volume and we have flown argon (from time to time) for a little while already. We need to wait a day or two before flowing the
operational gas to TPC. The C-AD Cryo group is busy with some works at 2 o'clock of RHIC today/this evening. But they'll do the necessary at 8 am tomorrow to start our Magnet cool-down. Since this is only the 2nd time, the Cryo Chief Engineer Roberto Than will need to work with the Cryo Control Room for quite a bit initially. STAR and other C-AD groups will also make use of this "access" time, as Paul Sampson will help coordinate. Kin -------- Forwarded Message -------- Good Afternoon Dr. Gao,
On behalf of Bob Gordon, attached please find the subject letter. If you have any questions, please contact Sean Tabone at ext. 3988 or via email at Sean.Tabone AT science.doe.gov.
Have a great day & stay safe!
Warm Regards, Monique Hemmerly Reporting Specialist III Contractor, Chickasaw Management Services, LLC In Support of: The U.S. Department of Energy Brookhaven Site Office 53 Bell Ave. Building 464 Upton, New York 11973 Phone: (631) 344-3431 Email: Monique.Hemmerly AT science.doe.gov
|
- [Sphenix-l] after approval ---> 8 am on May 19 to adjust nitrogen flow meter in IR and start to cool down the sPHENIX magnet, Yip, Kin, 05/18/2023
Archive powered by MHonArc 2.6.24.