Subject: sPHENIX is a new detector at RHIC.
List archive
- From: Rosi Reed <rosijreed AT lehigh.edu>
- To: "sphenix-l AT lists.bnl.gov" <Sphenix-l AT lists.bnl.gov>
- Subject: [[Sphenix-l] ] Fwd: Updating every one on Run-25
- Date: Wed, 19 Mar 2025 21:24:40 -0400
From: Deshpande, Abhay <abhay AT bnl.gov>
Date: Wed, Mar 19, 2025 at 5:08 PM
Subject: Updating every one on Run-25
To: Rosi Reed <rosijreed AT lehigh.edu>, Lee, Jeong-Hun <jhlee AT bnl.gov>, John Harris <john.harris AT yale.edu>, Huang, Jin <jhuang AT bnl.gov>, Megan Elizabeth Connors <mconnors AT gsu.edu>, Ruan, Lijuan <ruan AT bnl.gov>, Frank Geurts <geurts AT rice.edu>
Cc: Dunlop, James C <dunlop AT bnl.gov>, Fischer, Wolfram <wfischer AT bnl.gov>, Minty, Michiko <minty AT bnl.gov>
Dear Rosi, J-H, (Run Coordinators) and sPHENIX/STAR spokespeople:
(cc: John H., PAC Chair)
It’s only a few days before Run 25 starts. I was hoping to know something more from the DOE, but it does not look likely now. So, I thought I would update you all and make sure we are on the same page. Hence this note. I hope nothing here will surprise you.
At the moment the best we can plan is the following
(based a note from Wolfram):
- 24 Mar 2025 start 4K wave
- 30 Jun 2025 pause operation +14 cryo-weeks, comment: (Jul/Aug hottest months)
- 18 Aug 2025 resume operation + 0 cryo-weeks, comment: 7 weeks pause
- 30 Sep 2025 end of FY2025 + 6 cryo-weeks
- 22 Dec 2025 end of Run-25 +12 cryo-weeks, comment: based on FY26 guideline but absolutely nothing certain about this yet.
This is 20 cryo-weeks in FY2025. We need the FY2025 budget to know the actual number.
If we cannot afford 20 cryo-weeks in FY2025, based on advice from C-AD so far (and I will also consult with the experiments when we know more) we would want to start the second part for Run-25 (based on the knowledge of FY26 fund expectation) to be continuous with FY2025.
One reminder is the (Remote) PAC is planned on June 17-18, 2025 which is would be a source of advice – but more on the species of operation.
Cheers, Abhay
Abhay Deshpande
Associate Laboratory Director (interim) Nuclear and Particle Physics &
EIC Science Director
Brookhaven National Laboratory
Email: abhay AT bnl.gov
Phone: + 1 (631) 344-8783
--
Associate Professor, Physics Department
Lehigh University
(610)758-3907