News from C-AD and preparation for Run 25:
The RHIC bus short repair is progressing well. However, after a power dip late last week that shut down the cryogenic system for several minutes, electrical tests in both the blue and yellow rings failed. This seems unrelated to the original blue short and is likely caused by moisture; drying of the leads took place over the weekend and hi-potting will be performed this morning. As a precaution, welding the blue cryostats will be delayed until all issues are resolved. The updated schedule has RHIC fully cold on May 25th. BLIP and NSRL operations continue.