sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
- From: "Phillips, David B" <phillips AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: Re: [Sphenix-magnet-l] First truck
- Date: Wed, 25 Mar 2015 15:34:47 +0000
Items 5 (Steel Frames) and 6 (beam) are going to be stored outside (by RHIC
Block Yard).
Does anyone have any objections to this?
-----Original Message-----
From: sphenix-magnet-l-bounces AT lists.bnl.gov
[mailto:sphenix-magnet-l-bounces AT lists.bnl.gov] On Behalf Of John Haggerty
Sent: Wednesday, March 25, 2015 10:06 AM
To: sphenix-magnet-l AT lists.bnl.gov
Subject: [Sphenix-magnet-l] First truck
The first truckload of equipment has arrived and is being unloaded at
building 912.
--
John Haggerty
email: haggerty AT bnl.gov
cell: 631 741 3358
Attachment:
Attachment A - Statement of Work 283767 Rev 4.docx
Description: Attachment A - Statement of Work 283767 Rev 4.docx
-
[Sphenix-magnet-l] First truck,
John Haggerty, 03/25/2015
- Re: [Sphenix-magnet-l] First truck, Phillips, David B, 03/25/2015