Re: [Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912
- From: "Lambiase, Robert" <lambiase AT bnl.gov>
- To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "McKeon, William F" <wmckeon AT bnl.gov>
- Subject: Re: [Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912
- Date: Mon, 13 Apr 2015 20:10:33 +0000
Hi Kin,
This is a very comprehensive test procedure. I’d like to add a few details for the quench detection based on a first pass look of the documentation I saw this weekend.
- Coil balance – The two halves are not equal. The inner coil has a smaller aperture and 531 turns, while the outer coil has a larger aperture and 536 turns. The scaling factor to equalize the ramp voltage of the two halves should be determined. SLAC spent a bit of time doing this. We should determine this number.
- Quench – The dump switch was triggered if there was an instantaneous exceeding delta V of IST (50mV) or an integral (I haven’t seen the time constant yet) of the delta V by INTEG (I need to find out this number) exceeding 8V. The integrator was set to zero any time the delta V went below INTEG. Perhaps we should monitor this integral as well as the instantaneous trip vlaue. As far as I could tell, they didn’t use Ldi/dt in any calculations.
Bob
From: Kin Yip <kinyip AT bnl.gov>
Date: Monday, April 13, 2015 at 3:36 PM
To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
Cc: "McKeon, William F" <wmckeon AT bnl.gov>
Subject: [Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912
Date: Monday, April 13, 2015 at 3:36 PM
To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
Cc: "McKeon, William F" <wmckeon AT bnl.gov>
Subject: [Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912
Hi,
Joe Muratore has just sent me a draft plan for the low current test. ( Thanks Joe !! )
For convenience, I've just put his plan (in Word document) to the agenda page :
https://indico.bnl.gov/conferenceDisplay.py?confId=1105
Please read and you may comment to the mailing list; or otherwise we'll discuss this on Apr. 22, 2015.
Kin
Joe Muratore has just sent me a draft plan for the low current test. ( Thanks Joe !! )
For convenience, I've just put his plan (in Word document) to the agenda page :
https://indico.bnl.gov/conferenceDisplay.py?confId=1105
Please read and you may comment to the mailing list; or otherwise we'll discuss this on Apr. 22, 2015.
Kin
-
[Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912,
Kin Yip, 04/13/2015
- Re: [Sphenix-magnet-l] A draft plan for the sPHENIX Magnet Low Current Test in Bldg. 912, Lambiase, Robert, 04/13/2015
Archive powered by MHonArc 2.6.24.