[Sphenix-magnet-l] leak in the He pipeline of Valve Box,
Kin Yip, 09/03/2015
-
[Sphenix-magnet-l] leak in the He pipeline of Valve Box (2nd trial),
Kin Yip, 09/03/2015
-
Re: [Sphenix-magnet-l] leak in the He pipeline of Valve Box (2nd trial),
Ceruti, Raymond B, 09/03/2015
- Re: [Sphenix-magnet-l] leak in the He pipeline of Valve Box (2nd trial), Than, Yatming (Roberto), 09/03/2015
-
Re: [Sphenix-magnet-l] leak in the He pipeline of Valve Box (2nd trial),
Ceruti, Raymond B, 09/03/2015
-
[Sphenix-magnet-l] leak in the He pipeline of Valve Box (2nd trial),
Kin Yip, 09/03/2015
- [Sphenix-magnet-l] leak searching status, Kin Yip, 09/04/2015
- [Sphenix-magnet-l] Martin Berndt, Lambiase, Robert, 09/07/2015
- [Sphenix-magnet-l] sPHENIX Magnet Biweekly meeting on Sept. 9, 2015 at 1 pm (902 conference room), Yip, Kin, 09/08/2015
- [Sphenix-magnet-l] FW: Leak found, Yip, Kin, 09/08/2015
- [Sphenix-magnet-l] Brief Summary of Biweekly sPHENIX Magnet Meeting (Sept. 9, 2015), Kin Yip, 09/09/2015
-
[Sphenix-magnet-l] Fwd: Cryogenic Break,
Kin Yip, 09/17/2015
- Re: [Sphenix-magnet-l] Fwd: Cryogenic Break, Than, Yatming (Roberto), 09/17/2015
- [Sphenix-magnet-l] Voltage-tap connectors Found!!!, Kin Yip, 09/21/2015
- [Sphenix-magnet-l] sPHENIX Magnet Biweekly meeting at 1 pm (Sept. 23, 2015) in 902A ( Conference room ), Yip, Kin, 09/22/2015
- [Sphenix-magnet-l] Brief Summary of Biweekly sPHENIX Magnet Meeting (Sept. 23, 2015), Kin Yip, 09/23/2015
- [Sphenix-magnet-l] minimal/idealistic schedule/scenario for the Low-field test, Yip, Kin, 09/23/2015
- [Sphenix-magnet-l] sPHENIX Detector Status Meeting 9-24-15 is cancelled, dlynch AT bnl.gov, 09/23/2015
- [Sphenix-magnet-l] Break Repair continues ..., Kin Yip, 09/28/2015
- [Sphenix-magnet-l] The 10 remaining items in the ATS system have beem extended to Dec. 21, 2015, Kin Yip, 09/30/2015