Skip to Content.
Sympa Menu

sphenix-magnet-l - [Sphenix-magnet-l] Brief Summary of sPHENIX Magnet Biweekly meeting (Nov. 25, 2015)

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] Brief Summary of sPHENIX Magnet Biweekly meeting (Nov. 25, 2015)
  • Date: Wed, 25 Nov 2015 16:47:11 -0500


1. We have had to give way to the RF group to work the ERL tests so that we can't start the field-joint work on Monday (Nov. 30).
They have promised to finish their work on Dec. 15, 2015 and we can do whatever we want after that. Yousef has reminded us
that it's possible the RF group may finish their work before Dec. 15.

We need (Roberto's estimate):

~3 days to warm up the cryo system
5 days for the field-joint work (such as welding ....)

Hopefully by then, we're all ready for the final safety walkthrough --- we actually have a safety presentation on Dec. 8, which is
let those people know what they're going to expect/check.

Before the low-field test can start, we need

~10 days to cool down from room temp. to 80K and then 4 days to cool from 80K to 4.5 K.
[ During the nitrogen cool-down to 80K, the cryo system in ERL/VTF can be used if it's needed. ]

The last two weeks of Dec. are ~3.5/3 day weeks due to X'mas/New-Year holiday which is not convenient for scheduling. Adding
all these days to Dec. 15, the earliest time that we can do the low-field test would be early Jan. We can make the real plan
(in time) when the RF group completes their work.


2. During the meeting, we've discuss various things that need to be done before the low-field test can be performed.

--- Achim Franz told us that he's buying cables for his magnetic field measurement system and sent his probe etc. to be
calibrated (for the long distance). There are 2D probes and 1 D probes which are dealt with differently. In any case,
he expects to receive his cables/equipment back in a couple weeks.

--- During the meeting, we discussed a bit about how the cabling will be done. After the meeting, Paul Giannotti, Piyush Joshi and I
went to the sPHENIX Magnet in Bldg. 912 and it's clear that we'll need to talk with Dave Phillips about how/where the cables are
coming down from the top platform. There are more than 1 possible ways ... We hope to meet with Dave on Monday in 912 to
discuss this ...

--- Dave told us before the meeting that after discussing with D. Donaldson, it'd be the week of Dec. 21 when the electricians
will be available to do the cable tray. Ed O'Brien told us that they have one electrician available and we'll discuss with Dave to see
whether is possible to do the cable tray work earlier.

--- Ray Ceruti raised the question about the linear potentiometers. He told us that the 4 old ones left for us from BaBar were not reliable.
It's decided to purchase 4 new ones and we'll connect them to Joshi's DAQ system so that they can be read out for the test.

--- From the discussion with Ray and Roberto Than, it seems that they couldn't put in two new temperature gauges in time as the splices
were already wrapped up. But these two new temperature gauges were not needed for the low-field test. In addition, the Cryo group have
installed two other new temperature gauges (elsewhere).

--- The requisition order for the valve box extension work has been sent out and Ed's side is dealing with it. If all go well, I understand that this
work (managed by Central Shop and they may send some works outside BNL).

--- Jim Mills told us that so far he's not succeeded to gain fund to purchase the Maxwell part of ANSYS (which requires $24K) from C-AD, the
Superconducting Magnet Division and ITD. The sPHENIX project is considering whether it's worth buying this .... This is originally thought to use
ANSYS to do both the magnetic field calculation and the stress calculation. Some more thought have been discussed such as whether John
Cozzolino's high stress (>60 MPa) might be due to sharp edges/boundaries ... Achim has reminded us that Walter Sondheim has used "Opera" to do
the field calculations just like Wuzheng Meng's. Before the pCDR was written, Walter compared his results with Wuzheng's. He didn't mention any
major discrepancies that he's found.


https://indico.bnl.gov/conferenceDisplay.py?confId=1584




  • [Sphenix-magnet-l] Brief Summary of sPHENIX Magnet Biweekly meeting (Nov. 25, 2015), Kin Yip, 11/25/2015

Archive powered by MHonArc 2.6.24.

Top of Page