- From: EdwardOBrien <eobrien AT bnl.gov>
- To: sphenix-magnet-l AT lists.bnl.gov, "Yip, Kin" <kinyip AT bnl.gov>
- Subject: Re: [Sphenix-magnet-l] Closing in at the target ?!
- Date: Fri, 29 Jan 2016 16:37:55 -0500
Kin,
That is really good progress. Do we have a recent photo of the
magnet of the 912 floor that I can show to DOE when we
are down there next Tuesday?
Thanks.
Ed
On 1/29/2016 3:57 PM, Kin Yip wrote:
Hi,
I was just down at the Bldg. 912 and I saw "Sonny Dimauta and
Co." working on all the connections for the power supply/DAQ
Paul Orfin lonely
working at the platform ... and also Paul Giannotti telling me a
few things and Mel VanEssendelft looking for D. Phillips and
other people to sign on
the work permit (which I already sign) ...
I understand that :
1. The 4 linear potentiometers were all installed this morning
by Ray Ceruti / Sonny & Co.
2. Sonny & Co. are
making all the connections for the DAQ/power supply for the
low-field test. I've just called him again to ask him to make
the 100 A
connection so that D. Phillips can put some "barrier" around
them.
3. The not-so-good news is that though we probably got
4 hours' work from the Cryo group on Thursday, today since the
Booster power supply had
problem, the works (including the precious Cryo group) for the
CeC has been extended and so we didn't get as much work as from
the Cryo group
(only Paul was doing some vacuum stuff ...). I wonder
whether this has had any impact on us ... as we'll have a
walkthrough next Wed. (and I don't want to
delay it for the 3rd or 4th time !). I heard somebody mention
working over the weekend ??
3.1 A while ago, I thought that we'd not have time to purchase
all the pieces to use the big SLAC pumps (and we'll use the
smaller roughing pumps). But
probably due to our delay (!), now as D. Phillips/P.
Orfin/Tom Tallerico told me, we're just missing only two
Contactors to arrive. Tom thinks
that we will have them in time :-)
4. Paul Giannotti told me that
(i) probably he has found two more bad strain gauge connections
(=> a total of 4). Since the junction box has been closed,
he couldn't really check now.
The other channels should be good (though he only checked
some of them).
(ii) he will come in on Sat. or Sun. to make all the strain
gauge (plus the accompanying temperature) connections.
5. Mel and we are finishing the work permit ... We need to
finish this before the walkthrough next Wed.
Critical path is still on the Cryo system ... Paul Orfin told me
that there are still a bunch of small things to be
connected/done with the Cryo system and their pressure test.
It's a matter of whether he can have manpower in the Cryo group
.... Whenever any major system breaks, RHIC will be opened
and the Cryo group will go
to work on the CeC.
Let's hope that things don't break and the Cryo group can work
on sPHENIX Magnet !!!
Kin
_______________________________________________
Sphenix-magnet-l mailing list
Sphenix-magnet-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-magnet-l
|
Archive powered by MHonArc 2.6.24.