Subject: sPHENIX discussion of the superconducting solenoid
List archive
[Sphenix-magnet-l] sPHENIX Magnet biweekly meeting on Feb. 24 at 1:30 pm in the 902 conference room ... status
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] sPHENIX Magnet biweekly meeting on Feb. 24 at 1:30 pm in the 902 conference room ... status
- Date: Tue, 23 Feb 2016 19:50:52 +0000
There will be a sPHENIX Magnet biweekly meeting tomorrow (Feb. 24) at 1:30 pm in the 902 conference room:
Agenda (https://indico.bnl.gov/conferenceDisplay.py?confId=1801)
Cool-down begins / progress ? Cool-down ends ? AOB ( Please let me know if you have other things to talk about)
Rich Meier told me that he’s waiting for L. Masi to take the two new/working Flow Controllers to replace the non-working Flow Controllers (from BaBar). Rich told me that those two old controllers seem to only open or close, but can’t be 10% or 50% (etc.) opened.
I attach the HMI picture and you can see the two “Flow Cntrl” in the middle at the top which are not showing any nos. --- the culprit at the moment that prevents us from cooling down. |
Attachment:
2016-2-23 14-34.JPG
Description: 2016-2-23 14-34.JPG