Hi,
I’ve made a presentation about the schedule (made from Microsoft Project) for the High-Field Test in the PMG meeting (where B. Mueller et. al. discusses about the sPHENIX project). The Microsoft Project file was created mainly by J. Hock, J. Mills, P. Orfin, D. Phillips and myself.
The powerpoint presentation can be found here:
The Microsoft Project file can be found :
Especially to : Mike Anerella and Ray Ceruti:
We have put down the following :
--- line 19: 3 weeks for “Install VB Extension and Hook-up” (install the Extension while they finish the rest of steel building) --- line 26: 2 days for “Install Valve Box” --- line 35: 2 weeks for “Hook-Up Valve Box”
Please don’t hesitate to let us now if they’re far from enough ….