Thanks Tom for the update and I conveniently just pass it along to our mailing list.

Sent from my Verizon 4G LTE Smartphone

------ Original message------
From: Tallerico, Thomas N
Date: Thu, May 4, 2017 2:26 PM
To: Yip, Kin;
Cc: Mills, James A;Giannotti, Paul;Meier, Richard;
Subject:SPhenix cryo status update

As previously mentioned two temperature sensors are installed. When the other group is finished their work on the other side we will attach the other two sensors. Rich is combining his wirelists and simplifying them to make it easier for me to create wire run drawings.  This is taking some time as the lists are quite large. The Tefzel cable arrived today. It has not been uncrated yet.  It will be uncrated tomorrow. The order for the DSUB connectors was placed. Thanks tom