Hi Ray, Last Monday (Aug. 28), we optimistically talked about the possibility of installing the Valvebox this week. Unfortunately, from last Friday's scheduling meeting, C-AD doesn't have carpenters to install the staircases and the wooden platform/hand-rails as they need to work on LeReC/STAR which has been scheduled long time ago (as a part of the summer schedule). Bill Christie was only willing to review it again next Monday and see when they can get carpenters to work for us (sPHENIX Magnet High-Field Test). Therefore, you don't need to worry about installing Valvebox this week (at least). I'll communicate with you once I have got any kind of newer information :-) :-( Kin |
- [Sphenix-magnet-l] delay due to the lack of carpenters for a week or two, Kin Yip, 09/05/2017
Archive powered by MHonArc 2.6.24.