Skip to Content.
Sympa Menu

sphenix-magnet-l - [Sphenix-magnet-l] delay due to the lack of carpenters for a week or two

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "Ceruti, Raymond B" <rayc AT bnl.gov>
  • Cc: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] delay due to the lack of carpenters for a week or two
  • Date: Tue, 5 Sep 2017 13:00:59 -0400

Hi Ray,

Last Monday (Aug. 28), we optimistically talked about the possibility of installing the Valvebox this week.   Unfortunately, from last Friday's
scheduling meeting, C-AD doesn't have carpenters to install the staircases and the wooden platform/hand-rails as they need to work
on LeReC/STAR which has been scheduled long time ago (as a part of the summer schedule).   Bill Christie was only willing to review
it again next Monday and see when they can get carpenters to work for us (sPHENIX Magnet High-Field Test). 

Therefore, you don't need to worry about installing Valvebox this week (at least).  I'll communicate with you once I have got any kind