sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
[Sphenix-magnet-l] Revised Schedule: sPHENIX Magnet Valve Box Removal Schedule
- From: "Phillips, David B" <phillips AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Folz, Charles" <cfolz AT bnl.gov>, "Kobasiuk, Frederick D" <kobasiuk AT bnl.gov>, "Zoccoli, Patrick" <pzoccoli AT bnl.gov>, "Toldo, Frank A" <fatoldo AT bnl.gov>, "Biggs, John C" <biggs AT bnl.gov>
- Subject: [Sphenix-magnet-l] Revised Schedule: sPHENIX Magnet Valve Box Removal Schedule
- Date: Fri, 25 Jan 2019 17:19:09 +0000
Revised Schedule: 1/29 Tuesday Morning: Rigging for removal of Cryo equipment & coax line 1/29 Tuesday Afternoon: Riggers set-up stand for Valvebox 1/30-31 Wed/Thurs: Ray to prep for Valvebox removal 2/1 Friday Morning: Remove Valvebox 2/4 Electricians remove all power & tray from top platform 2/5-7 Removal of top platform and return yoke top steel
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov>
On Behalf Of Phillips, David B
Planned schedule for sPHENIX Magnet Valvebox removal:
1/30 Wednesday Morning: Rigging for removal of Cryo equipment & coax line 1/30 Wednesday Afternoon: Riggers set-up stand for Valvebox 1/31 Thursday: Ray to prep for Valvebox removal 2/1 Friday Morning: Remove Valvebox 2/4 Electricians remove all power & tray from top platform 2/5-7 Removal of top platform and return yoke top steel
Let me know if there issues with this schedule. There are still cables that need to be removed before the Electricians can remove the cable trays on 2/4.
Dave
David Phillips Building 911B Upton, NY 11973 631-344-4671, Fax 631-344-5954, Cell 631-804-9477
|