[Sphenix-magnet-l] Valvebox Removal and Tom Tallerico's videos
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Kobasiuk, Frederick D" <kobasiuk AT bnl.gov>, "Folz, Charles" <cfolz AT bnl.gov>, "Zoccoli, Patrick" <pzoccoli AT bnl.gov>, "Toldo, Frank A" <fatoldo AT bnl.gov>, "Biggs, John C" <biggs AT bnl.gov>
- Subject: [Sphenix-magnet-l] Valvebox Removal and Tom Tallerico's videos
- Date: Fri, 1 Feb 2019 20:16:06 +0000
Hello,
This morning, before/around 11 am, the riggers started setting up two concrete blocks on the floor. ( I am not sure where you found the blocks. 😊 )
This afternoon, after 1 pm, the riggers, with Brian Streckenbach, Ray Ceruti, Joe D’Ambra, Drew Carleton, and Frank Toldo et. al., lift the Valvebox from the platform and put it over the concrete blocks. The initial lifting off the junction-box is very very slow as a lot of adjustment needed to be done between the riggers and Ray and Joe. After the Valvebox was completely detached from the junction box, it’s relatively much swifter journey to the concrete blocks. I attach one picture that I took at the end of the removal process.
Frank Toldo has taken many pictures and he’ll give us soon.
Tom Tallerico has used his smartphone and GoPro video-recorder to record vidoes. His youtube links may be found here (that I’ve added to our sPHENIX webpage) :
https://collab.external.bnl.gov/sites/sPHENIX-Magnet/SitePages/Videos.aspx
He’ll put the 60 GB .mp4 files to the Babar disk server.
Kin
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov>
On Behalf Of Phillips, David B
Revised Schedule: 1/29 Tuesday Morning: Rigging for removal of Cryo equipment & coax line 1/29 Tuesday Afternoon: Riggers set-up stand for Valvebox 1/30-31 Wed/Thurs: Ray to prep for Valvebox removal 2/1 Friday Morning: Remove Valvebox 2/4 Electricians remove all power & tray from top platform 2/5-7 Removal of top platform and return yoke top steel
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov>
On Behalf Of Phillips, David B
Planned schedule for sPHENIX Magnet Valvebox removal:
1/30 Wednesday Morning: Rigging for removal of Cryo equipment & coax line 1/30 Wednesday Afternoon: Riggers set-up stand for Valvebox 1/31 Thursday: Ray to prep for Valvebox removal 2/1 Friday Morning: Remove Valvebox 2/4 Electricians remove all power & tray from top platform 2/5-7 Removal of top platform and return yoke top steel
Let me know if there issues with this schedule. There are still cables that need to be removed before the Electricians can remove the cable trays on 2/4.
Dave
David Phillips Building 911B Upton, NY 11973 631-344-4671, Fax 631-344-5954, Cell 631-804-9477
|
Attachment:
20190201_141339.jpg