sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done
- Date: Mon, 24 Jun 2019 19:28:44 +0000
Dear Ray,
When will you have time to come to Bldg. 912 to close out the old doghouse, and clean up/wrap the new doghouse (with plastic bag) --- without the two doors ? As soon as possible, I hope ?? Tom Tallerico et. al. have finished checking what they need to check.
The plan and steps are the following :
chimney etc. to connect everything with in a couple years, you can’t really do too much. But can you please carefully/nicely wrap those cables/wires and cover the new doghouse with plastic bag ? As the email below, Dave asks us not to cover with the new doghouse with doors to reduce weight for the next step.
Kin
From: Phillips, David B
Kin,
My understanding is that Paul’s transport support for the valvebox extension can’t be installed until after the cryostat is lifted from the return steel to the yellow transport frame. So it may be better not to close the “new” doghouse to reduce the weight on the extension until after the cryostat has been moved to the transport frame.
Dave
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov>
On Behalf Of Yip, Kin
Hi Tom Tallerico,
As you can see below, Carl & Fred & Joe D’ambra have finished with the voltage taps. ( Thanks to all of them ! )
Please proceed as we have discussed to check on the C-connectors next Monday (by R. Meier). When you finish checking, please let us know so that we can ask Ray Ceruti to close the doghouses.
Kin
From: Schultheiss, Carl
Hi,
Joe Dambra and I have finished this stage of testing of the sPhenix Magnet Voltage Taps. The magnet hi-potted to 520 V, and all the taps are present. Ray can finish closing the old dog-house and whatever is planned for the new dog-house. When the old dog-house is completely closed, and all the work on the new dog-house is complete, I think another round of testing should be done to insure everything is OK before we put the magnet away for its long sleep. I think we should buy some test equipment so we can do this sort of testing on our own.
Carl Schultheiss Principal Electrical Engineer Collider-Accelerator Department Brookhaven National Laboratory
|
Attachment:
20190624_142656.jpg
Description: 20190624_142656.jpg
-
[Sphenix-magnet-l] FW: sPhenix Voltage Taps Done,
Yip, Kin, 06/21/2019
- Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done, Tallerico, Thomas N, 06/21/2019
-
Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done,
Phillips, David B, 06/24/2019
-
Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done,
Yip, Kin, 06/24/2019
- Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done, Ceruti, Raymond B, 06/24/2019
-
Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done,
Yip, Kin, 06/24/2019
- Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done, Ceruti, Raymond B, 06/26/2019
-
Re: [Sphenix-magnet-l] sPhenix Voltage Taps Done,
Yip, Kin, 06/24/2019
Archive powered by MHonArc 2.6.24.