Skip to Content.
Sympa Menu

sphenix-magnet-l - [Sphenix-magnet-l] 11 payments changed to 24 payments (for Cryo Helium line procurement)

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] 11 payments changed to 24 payments (for Cryo Helium line procurement)
  • Date: Wed, 27 Nov 2019 16:47:08 +0000

Hi,

After the Cryo group (Paul and Roberto) asked the vendor (AET) for earlier delivery of some items (so that the Cryo may work with them next summer),
the vendor breaks down the payments more finely and the BNL procurement agrees.   Last week, with Irina, R. Gutta and Glenn, we included the schedule and
payments into the P6 (baseline).

P. Bernath just sent me the contract (after I asked him yesterday).  I put it here :

https://collab.external.bnl.gov/sites/sPHENIX-Magnet/Shared%20Documents/1008/2019-11-22%20Ability%20Contract%20362765%20Amendment%201.pdf

and you may compare with the original :

https://collab.external.bnl.gov/sites/sPHENIX-Magnet/Shared%20Documents/1008/2019-10-23%20Ability%20Contract%20362765%20-%20SIGNED.pdf

11 payments have become 24 payments but the total is the same : $1,565,660.35.


[  I've added the those 24 payments to verify that the sum is correct :-)  ]

Kin

PS: I noticed in this PDF version, the vendor has not signed yet.  But the payment schedule is vendor's proposal  :-) 


-------- Forwarded Message --------
Subject: RE: New contract with revised schedule ?
Date: Wed, 27 Nov 2019 10:27:53 -0500
From: Bernath, Philip <pbernath AT bnl.gov>
To: Yip, Kin <kinyip AT bnl.gov>
CC: Orfin, Paul <porfin AT bnl.gov>


Hi Kin,

 

See attached

 

Phil

 

From: Yip, Kin <kinyip AT bnl.gov>
Sent: Tuesday, November 26, 2019 1:51 PM
To: Bernath, Philip <pbernath AT bnl.gov>
Subject: New contract with revised schedule ?

 

Hi,

 

I understand that Paul Orfin and Roberto Than negotiated with AET and they got new schedule (including payments).  We actually put in the new schedule iNto P6.

 

Did you make a new contract ?  If so, can you send it to me, please ?

 

Kin



  • [Sphenix-magnet-l] 11 payments changed to 24 payments (for Cryo Helium line procurement), Yip, Kin, 11/27/2019

Archive powered by MHonArc 2.6.24.

Top of Page