From: Feder, Russell <rfeder AT bnl.gov>
Kin These are in P6 spread around and with some adjustments from me for it all to hang together...
Russell Feder Brookhaven National Lab sPHENIX Chief Mechanical Engineer 631-655-2491
From: Yip, Kin <kinyip AT bnl.gov>
Hi Russ,
Thanks a lot. These are the dates in your “plan”, not really in the official P6 (that Irina and Glenn discuss with us every month) , right ? Or are they ??
Kin
From: Feder, Russell <rfeder AT bnl.gov>
4. Roll in of the platform into the IP8 hall. --> around 4/6/22
Russell Feder Brookhaven National Lab sPHENIX Chief Mechanical Engineer 631-655-2491
From: Yip, Kin <kinyip AT bnl.gov>
Hi,
In the P6, do you guys have a date for any of the following items that Paul is interested in ??
4. Roll in of the platform into the IP8 hall.
There isn’t one in the Magnet section. I wonder whether there is such a date in your part of the P6 ??
Can you please advise ??
Kin
From: Yip, Kin
Hi Paul and Glenn,
To the best of my ability, I can only find the following two items which may be vaguely relevant to Paul.
281400 Magnet and Solenoid Valvebox – Reinstall Feb. 8, 2022 to Mar. 15, 2022. 281600 Magnet - Solenoid Valvebox - Complete, Ready for Cryo Connections Mar. 29, 2022
I’m not sure P6 has an item for each of Paul’s 4 points. I don’t have any of those spreadsheets/details related to infrastructure and installation.
Glenn, can you please advise ???
Kin
From: Orfin, Paul <porfin AT bnl.gov>
Kin,
I am looking to get dates for the following project events.
1. The move of the solenoid into the 1008 assembly hall 2. The move of the existing solenoid valve box into the 1008 assembly hall 3. The completion of the platform in the 1008 assembly hall so that we can begin to install the remaining cryogenic lines. 4. Roll in of the platform into the IP8 hall.
Thank you,