sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
Re: [Sphenix-magnet-l] Successful final PCSS review for the Cryo system
- From: "O'Brien, Edward" <eobrien AT bnl.gov>
- To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: Re: [Sphenix-magnet-l] Successful final PCSS review for the Cryo system
- Date: Tue, 19 Apr 2022 16:38:14 -0400
Hi Kin,
Thanks for the good news.
Ed
Hi,
We have just had a successful final PCSS (Pressure & Cryogenic Safety Subcommittee) and since there is no indico page, I’ve placed Paul’s talk in the calendar item:
https://brookhavenlab.sharepoint.com/sites/sPHENIXMagnet/External/Lists/Calendar/EditForm.aspx?ID=290
We’re approved by the PCSS to do installation. Before the Cryo operation can happen for the Magnet Mapping, mainly, there is one real action item
that we need to have an approved OPM (Cryo) before the Cryo operation for the Magnet Mapping. Roberto and Ken Hwang are working on it.
The other action item is for cryo test during installation which the Cryo group will do anyway during the Cryo installation.
{ Everybody knows that a USI process is on-going and needs to be completed before we can run the Cryo operation and do the Magnet mapping. David Mohamed
who is handling the USI actually helped us field two questions such as where the He/N sensors were placed --- it’s Roberto’s choice but I guess Roberto acted “neutral” not to
answer questions as he’s a PCSS member 😊 So, USI completion is not an explicit action item. }
Kin
_______________________________________________ sPHENIX-magnet-l mailing list sPHENIX-magnet-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/sphenix-magnet-l
-
[Sphenix-magnet-l] Successful final PCSS review for the Cryo system,
Yip, Kin, 04/19/2022
- Re: [Sphenix-magnet-l] Successful final PCSS review for the Cryo system, O'Brien, Edward, 04/19/2022