  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] FW: Scaffolding
  • Date: Mon, 11 Jul 2022 22:22:50 +0000

Thanks Jim for sharing the photo of the scaffolding.   If they get the remaining two rails tomorrow (Tue.), Valvebox transport (from 912 to 1008) can happen this Wed.

 

Kin

 

From: Mills, James A <mills AT bnl.gov>
Sent: Monday, July 11, 2022 5:09 PM
To: O'Brien, Edward <eobrien AT bnl.gov>; Feder, Russell <rfeder AT bnl.gov>; Yip, Kin <kinyip AT bnl.gov>; Toldo, Frank A <fatoldo AT bnl.gov>; Pontieri, Chris <cpontieri AT bnl.gov>
Subject: Scaffolding

 

Hi,

 

Scaffold is looking good.  

 

Also the last two rails for the N/S poletip doors are ready to be picked up at the shops.  We'll get them in the morning.  

 

Jim

 