sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
- From: "Feder, Russell" <rfeder AT bnl.gov>
- To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Masi Jr, Leonard" <masi AT bnl.gov>, "Moore, John J" <jmoore AT bnl.gov>
- Subject: Re: [Sphenix-magnet-l] connector done →
- Date: Thu, 21 Jul 2022 16:19:42 +0000
Kin
Thank you for helping us make this change to the doghouse voltage tap. It will help a lot with the install of TPC, INTT and MVTX.
Russ
Russell Feder
Brookhaven National Lab
sPHENIX Chief Mechanical Engineer
631-655-2491
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov> on behalf of Yip, Kin <kinyip AT bnl.gov>
Sent: Thursday, July 21, 2022 12:13 PM
To: sphenix-magnet-l AT lists.bnl.gov <sphenix-magnet-l AT lists.bnl.gov>
Cc: Masi Jr, Leonard <masi AT bnl.gov>; Moore, John J <jmoore AT bnl.gov>
Subject: [Sphenix-magnet-l] connector done →
Sent: Thursday, July 21, 2022 12:13 PM
To: sphenix-magnet-l AT lists.bnl.gov <sphenix-magnet-l AT lists.bnl.gov>
Cc: Masi Jr, Leonard <masi AT bnl.gov>; Moore, John J <jmoore AT bnl.gov>
Subject: [Sphenix-magnet-l] connector done →
Hi,
Dan Sullivan told me that they had finished changing the connector below the Doghouse. I just took a picture (attached).
We have just consulted with Ray Ceruti and Ray advised us that the Cryo group guys should install the temperature sensors and connect all the connectors, before Ray can wrap or clamp ...
After all these, Carl Schultheiss can do the hipot.
And (reminder) we need Ray and his colleagues to install MLI, heat shield on the opened side of the Valvebox and close the door .
Kin
Your enthusiastic reporter from the Doghouse scaffolding
-
[Sphenix-magnet-l] connector done →,
Yip, Kin, 07/21/2022
- Re: [Sphenix-magnet-l] connector done →, Feder, Russell, 07/21/2022
Archive powered by MHonArc 2.6.24.