Skip to Content.
Sympa Menu

sphenix-magnet-l - Re: [Sphenix-magnet-l] 2nd trial for the 24 hour run

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Edward O'Brien <eobrien AT bnl.gov>
  • To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
  • Subject: Re: [Sphenix-magnet-l] 2nd trial for the 24 hour run
  • Date: Wed, 26 Oct 2022 18:02:50 -0400

    Hi Kin,
     Good. Better luck this time. Thanks for the update.

    Ed

On 10/26/22 4:57 PM, Yip, Kin wrote:
Hi,

After fixing the firing board for the SCR (silicon controlled rectifier) in the Power Supply, we ramped up the current for the Magnet and reached the top current at 4:08 pm.

And we started our 2nd trial for the 24 hour run ...

Kin



_______________________________________________
sPHENIX-magnet-l mailing list
sPHENIX-magnet-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-magnet-l




Archive powered by MHonArc 2.6.24.

Top of Page