sphenix-magnet-l - [Sphenix-magnet-l] Mapping again ... 20 A power-supply current jump (walkie-talkie !) ... Pablo requests 1-2 days test after the mapping

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Mannel, Eric" <mannel AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
  • Subject: [Sphenix-magnet-l] Mapping again ... 20 A power-supply current jump (walkie-talkie !) ... Pablo requests 1-2 days test after the mapping
  • Date: Mon, 7 Nov 2022 20:42:31 +0000

Hi,


After the LOTO/pole-tip door business, we started ramping at 8:15 am and we reached the top about 10:03 am.   The mapper started taking data at 10:09 am for the 44-hour run.    I put quite some information in our C-AD Elog ( https://elog.pbn.bnl.gov:8181/elogs/entryList.jsp?DATABY=shift&ELOG=sPhenix&PAGE=1&DIR=backward&AUTO=yes&MODE=ALL#1669362 ) --- inside C-AD firewall of course.

There are typically fluctuations in the currents, slightly more for the power-supply current than the magnet current.
But around 1:39 pm, I saw a ~20 A jump in the power-supply current and luckily it went away quickly (a few seconds) and only caused ~1 A jump
in magnet current, and no noticeable damage was done.   ( You may remember that we saw a rise of ~400 A for 85 s on Oct. 26 which eventually tripped the Power-Supply and therefore Magnet due to crowbar over-temperature. )  I attach the plot for the current rises and the gas-cooled-leads (voltage taps) actually also saw the jump as well.

I emailed with Pablo/Carl.  A few minutes later when I called Pablo, we discussed and apparently at that time, a CAS person was using radio/walkie-talkie in 1008B mezzanine --- close to our Power Supply.  Pablo said that he'd seen this before and the strong RF signal can trigger disturbance like this.   I was told that we actually have a sign in 1008B (probably on 1st floor) to tell people not to use radio.  ( I'm going to take a look later ... ) 

And by the way, for things like this (Pablo wants to see whether radio signal on 1st floor would affect the Power Supply), Pablo requests a 1-2 day test after the mapping.   We can ramp down the Magnet to take out CERN equipment if necessary and ramp the magnet back up.  Pablo's test can be done easily as long as we do keep the Cryo at He temperature.  We have to remember not to warm up immediately after the mapping is done. 

John Haggerty is taking over after 4 pm ... Eric Mannel will do the "00:00 to 08:00" shift.

Kin

Attachment: tmpPrintEmailY5b0kT.gif
Description: tmpPrintEmailY5b0kT.gif

Attachment: tmpPrintEmailY5b0kT.gif
Description: tmpPrintEmailY5b0kT.gif