sphenix-magnet-l - [[Sphenix-magnet-l] ] Hipot on the sPHENIX Magnet was completed successfully ... need to remember to put back on the fan on the Current Leads.

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: CRYO GROUP <cryogroup AT brookhavenLab.onmicrosoft.com>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Cc: "Albanese, Marianna" <malbanese AT bnl.gov>
  • Subject: [[Sphenix-magnet-l] ] Hipot on the sPHENIX Magnet was completed successfully ... need to remember to put back on the fan on the Current Leads.
  • Date: Wed, 12 Feb 2025 21:04:31 +0000

Hello,

 

Carl Schultheiss together with Theo Samms and Jonathan Zubarriain did a hipot on the sPHENIX Magnet at about ~120 K (depending on which temperature sensors

you look at) successfully just before 3 pm.   Attached was the picture that Carl took and sent to me.  You can see our standard hipot voltage 520 V with

leakage current only at 0.10 mA.    John Haggerty and I are both happy to see “no hiccup” or accident of any sort this year.

 

One thing to remember:  Since I needed to stand around the Current Leads to prevent people approaching/touching it during the hipot, I noticed that

the power strip that powers the fan on top of the Current Leads and probably also dry air was disappeared.   I went to Ken Riker and Dan Martin and

they told me that they took the power strip away during the shutdown.  We all agree that we need to remember to put it back in a month before the

RHIC run starts 😊

 

Kin

 

From: Yip, Kin
Sent: Tuesday, February 11, 2025 1:47 PM
To: Than, Yatming (Roberto) <ythan AT bnl.gov>; CRYO GROUP <cryogroup AT brookhavenLab.onmicrosoft.com>
Subject: RE: sphenix high pot Wednesday or Thursday.

 

We’re trying to do it tomorrow (Feb. 12) at 2 pm.   There is nothing that you guys need to do or worry (in principle).

 

Kin

 

From: Than, Yatming (Roberto) <ythan AT bnl.gov>
Sent: Tuesday, February 11, 2025 9:59 AM
To: CRYO GROUP <cryogroup AT brookhavenLab.onmicrosoft.com>
Cc: Yip, Kin <kinyip AT bnl.gov>
Subject: sphenix high pot Wednesday or Thursday.

 

The solenoid will be hi-potted either on Wednesday or Thursday.

Carl Schultheiss will perform the hi-pot.

I signed off on the work permit.

The plexiglass box remains in place.

Signs will be posted.

The highpot side is done from 1008B.

 

Roberto

 

 

Attachment: Resized_20250212_145755.jpeg.jpg
Description: Resized_20250212_145755.jpeg.jpg



  • [[Sphenix-magnet-l] ] Hipot on the sPHENIX Magnet was completed successfully ... need to remember to put back on the fan on the Current Leads., Yip, Kin, 02/12/2025