[Sphenix-maps-l] MVTX DOE full proposal overleaf link and bi-weekly meetings
- From: "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>
- To: sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>
- Cc: Sanghoon Lim <shlim1986 AT gmail.com>, Xuan Li <xuanli AT bnl.gov>
- Subject: [Sphenix-maps-l] MVTX DOE full proposal overleaf link and bi-weekly meetings
- Date: Tue, 05 Sep 2017 22:44:17 -0600
From: <owner-sphenix-ldrd AT maillist.lanl.gov> on behalf of "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>
Date: Thursday, August 31, 2017 at 08:35
To: sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>, sPHENIX LDRD <sphenix-ldrd AT lanl.gov>
Cc: "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>, "Chamizo Llatas, Maria" <mchamizo AT bnl.gov>, Robert Redwine <redwine AT mit.edu>, Grazyna Odyniec <g_odyniec AT lbl.gov>, "Huang, Jin" <jhuang AT bnl.gov>, "XDong AT lbl.gov" <XDong AT lbl.gov>, Gunther Roland <rolandg AT mit.edu>, "Morrison, David" <morrison AT bnl.gov>
Subject: MVTX workfest Dec. 5-7 @Santa FeDear all,Following the very positive recommendations from the recent MVTX BNL Directors Review, we propose to move forward to prepare for the full proposal submission to DOE by early 2018 (~Jan. 2018?).After some discussions, we think a dedicated workfest in early December before the sPHENIX Collaboration Meeting would be timely to push for the completion of the full proposal by the end of this year.MVTX workfest: Dec. 5-7 (Tue-Thu.), 2017, Santa Fe, NMsPHENIX Collaboration: Dec. 8-10, Santa Fe, NMHere is a summary of action items and proposed timelines (draft, to be discussed with ALD and review committee ) following the Directors Review Recommendations:1. Solicit multiple theory predictions – December 2017
2. Refine the three key physics plots – October 2017
3. MoU with CERN for stave production – December 2017
4. Refine cost estimate with CERN – DONE
5. QA plan for tests (readout and cooling needs at LBNL and BNL) – October 2017
6. Cost of building two inner layers – DONE
7. Scenarios for repair and replacement – October 2017
8. Refine estimates for engineering design - End September- 2017
9. Include Cost of Extension cables – End September 2017
10. Consider including UV sterilization of demineralized water in cooling plant, October 2017
11. MoU with key production sites – December 2017
12. Optimize design of INTT and MVTX simultaneously – Feb-March 2018 – this will need sometime
13. Re-evaluate mechanical engineering costs once INTT and MVTX are final – after March 2018 (– too late?).
- related to #8 & #9, here one should make sure that the contingency is properly estimated to absorb cost variations due to different designs.
realistic contingency on carbon structures – End September 2017
14. Develop a Project Management Plan – September 2017, a draft available
– how detailed this plan needs to be at this stage of the project, further discussion with ALD/DOE. If PMP needed draft by October 2017
15. Clearly define scope, WBS dictionary, deliverables – October 2017
– not sure if all this is needed at this stage of the project, but can be done, further discussion with ALD/DOE
16. Evaluation and documentation of risks – October 2017Maria, Grazyna, Bob, Xin, Jin and Ming--Ming Xiong LiuP-25, MS H846TEL:505-667-7125Physics Division631-344-7821(BNL)LANL630-840-5708(FNAL)Los Alamos, NM 87545FAX:505-665-7020