sphenix-maps-l AT lists.bnl.gov
Subject: sPHENIX MAPS tracker discussion
List archive
Re: [Sphenix-maps-l] [Sphenix-l] MVTX Review Close out at 1:00 pm, 2-160
- From: "O'Brien, Edward" <eobrien AT bnl.gov>
- To: Ming Liu <ming AT bnl.gov>, "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>, sphenix-mvtx-l <sphenix-maps-l AT lists.bnl.gov>, Glenn Young <glennyoung82251 AT gmail.com>, "Lavelle, Cathleen B" <lavellec AT bnl.gov>, "haggerty AT bnl.gov" <haggerty AT bnl.gov>, "mills, James A" <mills AT bnl.gov>, "rfeder AT bnl.gov" <rfeder AT bnl.gov>, "Sourikova,Irina V" <irina AT bnl.gov>, "Gutta, Rajendra Rao" <rgutta AT bnl.gov>, James E Kelsey <jkelsey AT mit.edu>, Jason Bessouille <jason_b AT mit.edu>, Joseph L Dodge <jdodge AT mit.edu>, HENP Team <p25henp-l AT lanl.gov>, sPHENIX LDRD <sphenix-ldrd AT lanl.gov>
- Cc: David Meyerhofer <dmey AT lanl.gov>, Joseph Carlson <carlson AT lanl.gov>
- Subject: Re: [Sphenix-maps-l] [Sphenix-l] MVTX Review Close out at 1:00 pm, 2-160
- Date: Tue, 30 Jul 2019 18:19:35 -0400
Dear all,
I completely agree with Ming's assessment of the review.
The MVTX review had a very positive outcome.
I'd like to especially thank Ming and his team, as well of the sPHENIX
Project team, for making this turn out well. You all produced a very
comprehensive set of talks and project documents that convinced the
review committee that we can begin this project after addressing a few
reasonable recommendations. Congratulations and thanks to all
who contributed.
Ed
On 7/30/2019 4:10 PM, Ming Liu wrote:
Dear all,
As Ed expected below, we did receive very good and positive MVTX Cost &
Schedule Review report at the Closeout, thanks for everyone's hard work that made
this review a success.
The final report should be available by the end of this week.
The committee also suggested to update the PMP to address a few technical
details regarding KPP, UPP, contingency etc. by the end of August, and we
will work on them in coming weeks.
As presented in the review, the project starting date is in September, Ed and
I discussed to have a phone meeting with DOE late Aug/early Sept to get all
the paperwork ready in time;
In the meantime, BNL is providing some early R&D fund for MIT/LBNL engineers
to work on a few critical issues related to carbon structure design and
production.
Cheers,
Ming
-
[Sphenix-maps-l] MVTX Review Close out at 1:00 pm, 2-160,
O'Brien, Edward, 07/30/2019
-
Re: [Sphenix-maps-l] [Sphenix-l] MVTX Review Close out at 1:00 pm, 2-160,
Ming Liu, 07/30/2019
- Re: [Sphenix-maps-l] [Sphenix-l] MVTX Review Close out at 1:00 pm, 2-160, O'Brien, Edward, 07/30/2019
-
Re: [Sphenix-maps-l] [Sphenix-l] MVTX Review Close out at 1:00 pm, 2-160,
Ming Liu, 07/30/2019
Archive powered by MHonArc 2.6.24.