Dear Antonello, Sure, next week July 9th actually also works better for us. Cheers, Ming
-- Ming Xiong Liu P-25, MS H846 TEL: 505-667-7125 Physics Division 631-344-7821(BNL) LANL 630-840-5708(FNAL) Los Alamos, NM 87545 FAX: 505-665-7020
From: Antonello Di Mauro <Antonio.Di.Mauro AT cern.ch>
Dear Ming,
I hope you are doing fine.
The production is progressing according to schedule however next week we will have more news on other topics like metrology, FPC production, chip testing, etc. Therefore, despite what we agreed two weeks ago, I propose to postpone our meeting to next week.
Please let me know if you agree.
Best regards
Antonello
|
-
[Sphenix-maps-l] sPHENIX stave production meeting,
Antonello Di Mauro, 07/01/2020
- Re: [Sphenix-maps-l] sPHENIX stave production meeting, Ming Liu, 07/01/2020
- Re: [Sphenix-maps-l] sPHENIX stave production meeting, Antonello Di Mauro, 07/08/2020
Archive powered by MHonArc 2.6.24.