  • From: Ming Liu <ming AT bnl.gov>
  • To: sphenix-mvtx-l <sphenix-maps-l AT lists.bnl.gov>, Walter Sondheim <sondheim AT lanl.gov>, James E Kelsey <jkelsey AT mit.edu>, Jason Bessouille <jason_b AT mit.edu>, Joseph L Dodge <jdodge AT mit.edu>
  • Subject: [Sphenix-maps-l] FW: "end-game" sPHENIX installation
  • Date: Tue, 08 Sep 2020 17:10:08 -0600

FYI,

MVTX and other sPHENIX subsystem installation duration – subject to further discussion:

 

        Days.     Activity

   

6

Install half-barrel #1 MVTX

5

Install half-barrel #2 MVTX

2

Align/survey MVTX

3

Install MVTX remaining cables/services

MVTX then continues 5d ORR, 5d action items from ORR, 5d commissioning

 

 

Cheers,

Ming

 

-- 

Ming Xiong Liu

P-25, MS H846                     TEL: 505-667-7125 

Physics Division                            631-344-7821(BNL)

LANL                                               630-840-5708(FNAL)

Los Alamos, NM 87545      FAX:  505-665-7020

 

 

From: Glenn Young <glennyoung82251 AT gmail.com>
Date: Monday, September 7, 2020 at 11:42 AM
To: Edward O'Brien <eobrien AT bnl.gov>, John Haggerty <haggerty AT bnl.gov>, Jim Mills <mills AT bnl.gov>, "Feder, Russell" <rfeder AT bnl.gov>, "Vasquez, Joel" <jvasquez AT bnl.gov>, Thomas Hemmick <tkhemmick AT gmail.com>, Craig Woody <woody AT bnl.gov>, John Lajoie <lajoie AT iastate.edu>, eric mannel <mannel AT bnl.gov>, "Martin L. Purschke" <purschke AT bnl.gov>, Mickey Chiu <chiu AT bnl.gov>, Caroline Riedl <criedl AT illinois.edu>, "Stoll, Sean" <stoll AT bnl.gov>, Stefan Bathe <bathe AT bnl.gov>, Megan Connors <meganEconnors AT gmail.com>, Steve Boose <boose AT bnl.gov>, Christopher Pontieri <cpontieri AT bnl.gov>, Robert Pisani <pisani AT bnl.gov>, Bob Azmoun <azmoun AT bnl.gov>, "Streckenbach, Brian" <bstreckenbach AT bnl.gov>, Chengyi Chi <chi AT nevis.columbia.edu>, Jamie Nagle <jamie.nagle AT colorado.edu>, "Ming Liu (BNL)" <ming AT bnl.gov>, "Nouicer, Rachid" <nouicer AT bnl.gov>, "Cacace, Daniel" <dcacace AT bnl.gov>, John Kuczewski <jkuczewski AT bnl.gov>, "Sourikova,Irina V" <irina AT bnl.gov>, "Gutta, Rajendra Rao" <rgutta AT bnl.gov>, "Lavelle, Cathleen B" <lavellec AT bnl.gov>, David Morrison <dave AT bnl.gov>, Gunther Roland <rolandg AT mit.edu>
Subject: "end-game" sPHENIX installation

 

Dear sPHENIX colleagues

The part of sPHENIX installation after the magnet is mapped is going to be a subject of increasing discussion based on recent meetings with CAD people.

I thought it would be useful to write down what we have in P6 that sets the timeline post-mapping. Please see the attached spreadsheet. 

In particular TPC, beampipe, INTT, and MVTX figure into the timeline.  MBD is assumed to be done in parallel with the silicon detectors.

 

This ought to form a basis for further discussion.  I am sure we'll have several chances to present this to various groups going forward. ;-)

Regards, Glenn

Attachment: Durations for Post-Mapping Installation P6 Sept 7 2020.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet



  • [Sphenix-maps-l] FW: "end-game" sPHENIX installation, Ming Liu, 09/08/2020