Dear all,
Here is the latest update of MVTX commissioning/installation weekly schedule for Feb-Mar:
Given the rapid progress with BP installation in IR, our schedule is moved up by ~ 1day:
160)install MVTX installation fixtures and test: Mar. 17 –> Mar. 16
(170) install half-detectors: Mar. 22 --> Mar. 21
(192) full daq checkout Mar. 28
Cameron will discuss commissioning shift planning for March at Monday’s MVTX meeting.
Cheers, Ming
|