John, Jim-
Today's review went well. I know that there are still a lot of open questions about moving components to the west side, but I am confident that our engineering staff can figure that out.
While it was stated that only 2 petals of the sEPD (1 north, 1 south) need to be removed, I would recommend that the engineering staff, along with sPHENIX techs take a close look to verify that there are not any other infrastructure components that might need to be moved (e.g. power cables, fibers, cooling lines...) for the sEPD and other detectors.
Eric
On 1/16/24 1:11 PM, John Haggler via Phoenix-MAPS-l wrote:
Hello,
Jim is having a design review of the absorber that has been designed to give us an option for shielding the MVTX from background. The review is tomorrow, Wed, Jan 17 at 3pm. The agenda is here:
https://indico.bnl.gov/event/21803/
and the Zoom link is here:
https://bnl.zoomgov.com/j/1606920062?pwd=N3NEdnA3UnkwYjFYYXZTcFN3cUQ4QT09
---
John Haggerty
haggerty AT bnl.gov
cell: 631 741 3358
_______________________________________________
sPHENIX-MAPS-l mailing list
sPHENIX-MAPS-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-maps-l
--
Eric J. Mannel, Ph.D.
Research Engineer
Dept of Physics/PHENIX
Brookhaven National Laboratory
631/344-7626 (Office)
914/659-3235 (cell)
-
[Sphenix-maps-l] Absorber review,
John Haggerty, 01/16/2024
- Re: [Sphenix-maps-l] Absorber review, John Haggerty, 01/17/2024
- Re: [Sphenix-maps-l] Absorber review, Eric Mannel, 01/17/2024
Archive powered by MHonArc 2.6.24.