sphenix-sepd-l AT lists.bnl.gov
Subject: sPHENIX Event Plane Detector discussion
List archive
[sphenix-sepd-l] sEPD - follow up short summary (1/21/2023)
- From: Jamie Nagle <jamie.nagle AT colorado.edu>
- To: Ron Belmont <belmonrj AT gmail.com>
- Cc: "sphenix-sepd-l AT lists.bnl.gov" <sphenix-sepd-l AT lists.bnl.gov>
- Subject: [sphenix-sepd-l] sEPD - follow up short summary (1/21/2023)
- Date: Sat, 21 Jan 2023 13:52:19 -0700
Hello Ron and sEPD list,
Here is a short summary on sEPD items following last week's meeting on Tuesday (01/17/2023)
- thanks to Ron for the minutes and particularly thanks to Russ and John H for key inputs.
Here is a list of the key items, their status, and critical items for the upcoming week.
* Mechanical support structure -
This structure holds up the sEPD and also the VESDA (Very Early Smoke Detection Apparatus) system. The planned installation of this structure is for the week of April 1-7, 2023. If the structure is not ready, a unistrut system would be installed for the VESDA system - since it is needed for the whole experiment. That would mean not having the sEPD in for Run-2023.
The main components for this structure are being made at the Astro Machine Works company in PA (https://astromachineworks.com/). Rosi has re-contacted them last week and they estimate delivery to BNL on March 26, 2023.
This order needs to be followed very carefully. The additional components to attach the structure to sPHENIX are being ordered/coordinated by Russ.
* Strongback support plates and petals -
These large aluminum plates (6 per side, so 12 total) are what the sEPD sectors are mounted to and then attached to the mechanical support structure detailed above. The status is that the drawings are now complete, though final detailing and checking are needed. There is sufficient detail to go out to machine shops / companies for bids.
Rosi has sent the drawings to MarkZero, the company that machined the scintillator, for bid. Jamie has met with two machine shops in the University of Colorado Boulder to check on options here, including requesting a bid from a local company.
It is critical to get this moving and have a first item, including associated hardware to test the mounting before building the full set.
--> In the discussion last week, it was stated that these plates with the sectors could be installed during a 12-hour access after beam start. That might relax the deadline for delivery. That might also be desirable since once they are mounted, one will lose access to the MBD, and the end of the TPC and inner detectors (which would then require taking the plates back down). It would be good to go over this choreography to understand how the plates would be moved into the IR and mounted if post-beam-start.
* SiPM Electronics Box -
The design is now complete, though with finishing detailing and drawings remaining. I do not have complete information on the status/requirements for fabrication yet in my notes. A key is that once complete, this needs full testing, integration in the High Bay well before it could be installed in the IR.
The design is now complete, though with finishing detailing and drawings remaining. I do not have complete information on the status/requirements for fabrication yet in my notes. A key is that once complete, this needs full testing, integration in the High Bay well before it could be installed in the IR.
* Meritec Cables -
The order has been placed and the status for delivery is not yet known.
It is a critical item for this next week to get a copy of the contract, and have a contact with them on status/delivery.
A proposal (which sounds good) is to ask Eric Mannel to help with this followup as he has significant dealings with this company.
The critical date by which these need to be installed/routed from the SiPM Electronics Box locations to the racks is not yet documented.
* SiPM Electronics Boards -
The order has been placed with CEC and the status for delivery is not yet known.
It is a critical item for this next week to get a copy of the contract, and have a contact with them on status/delivery.
A proposal (which sounds good as above) is to ask Eric Mannel to help with this followup as he has significant dealings with this company too. The SiPMs which get mounted last are still at Lehigh. We need four "first article" boards ASAP for testing -- at the High Bay for the cosmic tests ideally. The priority is actually testing the boards to have the remainder produced, and a side benefit is speeding up the cosmic tests.
* ADC Racks/Crates/Boards - after some checking by Dan / John H, the rack is on the list to be plumbed by Damon (confirmed by Steve Boose). There will be just one ADC crate -- Dan has identified a crate/backplane.
* Fiber bundles - the bundles are complete at Lehigh except the end connector. Putting on the end connectors is waiting for one SiPM board to check the alignment. The critical date by which these need to be installed/routed from the sEPD detector location to the SiPM Electronics Box locations is not yet documented.
* Sectors - overall these are in good shape. Cosmic testing is proceeding now, though less efficiently without the SiPM boards.
The sectors are not the schedule-driver at this point.
Organization... Rosi and I have agreed to copy all emails to both of us - providing better coverage and responsiveness. At the sPHENIX Operations Board meeting, I will cover when Rosi is unavailable. At the meeting this past Friday, the key points above were discussed and hopefully digested. We are also setting up a weekly engineering/technical meeting with Rosi, myself, Russ, John H. that will be particularly important moving towards full installation.
That is all for today ahead of Monday's regular sEPD meeting.
Sincerely,
Jamie
||------------------------------------------------------------------------------------------
|| James L. Nagle
|| Professor of Physics, University of Colorado Boulder
|| James L. Nagle
|| Professor of Physics, University of Colorado Boulder
|| EMAIL: jamie.nagle AT colorado.edu
|| SKYPE: jamie-nagle
|| WEB: http://spot.colorado.edu/~naglej
||------------------------------------------------------------------------------------------
|| SKYPE: jamie-nagle
|| WEB: http://spot.colorado.edu/~naglej
||------------------------------------------------------------------------------------------
On Fri, Jan 20, 2023 at 12:07 PM Ron Belmont <belmonrj AT gmail.com> wrote:
Hi All,
I think it would be helpful if people replied to the list by the end of the day today letting us know what progress has been made on the key action items from the meeting on Monday.
Regards,
Ron
-----------------------------------------------------------------------------
Ron Belmont (he/him/his)
RHIC/AGS Users' Executive Committee
Assistant Professor, Department of Physics & Astronomy
University of North Carolina at Greensboro
-----------------------------------------------------------------------------
On Jan 17, 2023, at 5:29 PM, Ron Belmont <belmonrj AT gmail.com> wrote:
Hi All,
Here are the minutes from today’s meeting. I made a short-ish executive summary and below that reproduce everything I had time to type during the meeting. The key action items are following up on various orders - Jamie is going to make a detailed summary of that and share it with key people tonight.
Regards,
Ron
** executive summary **
We have a general consensus that there is likely a need to hold off on installing the sEPD sectors until after a few weeks of beam. We want to avoid installing and uninstalling the sectors too many times, and the tracking system and the MBD will likely need a lot of access during the first few weeks.
The support structure is needed for other essential systems like VESDA. There’s an alternate structure that can be made if needed, but getting in touch with ASTRO to make sure it gets completed is a high priority. Alternately, it may be possible to build the support structure elsewhere. Russ will share the drawings with Jamie who will check if it can be built by the shop at CU. The go or no go date for the support structure is the first week of April (3–9). Further follow up on this, like designating a point person for contact, to take place.
The SiPM boards are being built by CEM. We need a first article ASAP. This could be one board or four. Contacting CEM to make sure these boards get built ASAP is a high priority. The SiPMs needed for the boards are at Lehigh. Rosi can hand deliver the SiPMs to CEM if necessary. Further follow up on this, like designating a point person for contact, to take place.
The order for Meritec cables has been placed. Following up with Meritec to ensure the cables are delivered is a high priority. Further follow up on this, like designating a point person for contact, to take place.
** sEPD support structure **need to support VESDA - have alternate design if needed, but better to have sEPD supportsASTRO - machine shop company that's building the sEPD support - Russ offered to take communication info and hound themKin on Friday - a go or no go date - latest milestones from Maria - first week in April (3-9) - if support from ASTRO not ready then need to use other strutwant to avoid taking sEPD in and out a bunch of times - might be better to wait until tracking is commissioned before installing - same could be true for MBD as well (since MBD access is mostly blocked by presence of sEPD)
what is time scale - how long does it take to mount the active sectors? are the cables already in? a day or two days? exclusive access?first time install - 6 hours for both sidesscintillator gets mounted to strongback ahead of time (doesn't need to be done in situ)strongback goes up quicklyfiber connectors quick as long as fiber routing is set, which it is (Dan Cacace)once we're in - the MBD won't be readily accessible - once we're there they can't touch stuff
there is potentially a scenario in which you don't want to install the sEPD sectorswant to run the optical fibers in advancefiber bundle connectors from detector to boxmeritec cables on order - need to check with them
get everything cabled but then wait for a couple of weeks into beam time before installingRuss - have some components (strongback) to construct that might not be ready anyway - made some simplification to design - those still have to be machined - can be made by any machinist but too big to be made at Lehigh - can possibly be made at Colorado shop - need drawings to show to Colorado shop - Stony Brook also an optiondrawings are finished, Russ is communicating with Rich to get status of drawingsdo not need to additional support for cracked sectors (maybe add some additional glue)
all racks are there - sEPD rack may not be populated - not sure if enough crates (but definitely have enough ADC boards)
** SiPM boards **ordered from CEM - need to follow up with them, but the boards are very simpleSiPMs are already at Lehigh, need to send to CEMmore made than neededneed four right away, Rosi can hand-deliver SiPMsJohn can get Eric to deal with CEManother possibility - get Eric to bug the meritec people
** from last week **cosmics tests not so informative since we don't have the gainsif we knew we were getting the boards in, say, two weeks, we would waitwould be good to get a first article to make sure that the SiPMs aren't placed incorrectly - first article could be the four we need initially
beginnings of actual electronics boxscrounging around for most partsaccess for electronics box? outside on the side - needs water cooling, provisions for that - box needs to be constructed and tested (e.g. in high bay) before installing in situ (location on detector is not so convenient)
odd side 11, 12, 13, 15 tested over weekend, 17 being tested now2 days per sectortotal of 9 sectors done, 21 remaining5 odd and even both done4 sectors odd onlynow that EMCal isn't there - can put the counters closer together (20 cm instead of 70 cm, ~4 times the rate)another 40-50 days of someone going over there multiple times a day - but if we had the SiPM boards that reduced by 2, and it could be reduced further if you can test more than one sector at a time - keep running tests like this but hope for more electronics soon...
ASTRO, Meritec, CEM... high priorities, issues with companies being delayed and not communicating, need to bug them ASAPdo we need a point person (permanently at BNL for next 4 months) sitting at regular engineering meetings
putting things in later - should be propagated into a real schedule? - which schedule is "real" is not so clear
Dan C is working on box, but that box is very similar to EMCal box - the design is completed, details/drawings need to be completedsuggestion to have shared directory for various drawings - Russ will setup and Indico page
approximately infinite CAD labor available to us currently - should take advantage of it as much as possibleall fiber bundles assembled, need to put ends on for mating to SiPM boards
** material scan **theta definition from geanttheta values for acceptance shown on slide 2 but not on later slides (Ejiro will update plots later)Ejiro will redo study when more stuff (support structures, services, etc) added to simulations
-----------------------------------------------------------------------------
Ron Belmont (he/him/his)
RHIC/AGS Users' Executive Committee
Assistant Professor, Department of Physics & Astronomy
University of North Carolina at Greensboro
-----------------------------------------------------------------------------
On Jan 16, 2023, at 11:51 AM, Ron Belmont <belmonrj AT gmail.com> wrote:
Hi All,
Given the urgent need to meet to discuss the electronics and other issues, please reply letting us all know availability. So far we’ve heard from John H and Dennis that they’re available tomorrow (Tues Jan 17) at 4pm so it’s shaping up to be a good time. I’ve gone ahead and made an agenda page for tomorrow at 4pm EST - it can be changed if we settle on a different time but we need to decide that ASAP.
Regards,
Ron
-----------------------------------------------------------------------------
Ron Belmont (he/him/his)
RHIC/AGS Users' Executive Committee
Assistant Professor, Department of Physics & Astronomy
University of North Carolina at Greensboro
-----------------------------------------------------------------------------
On Jan 15, 2023, at 3:15 PM, Jamie Nagle <jamie.nagle AT colorado.edu> wrote:
Hello Ron and sEPD list,
We really need to have a meeting in person this next week.
Can I propose we just move the meeting back a day to Tuesday at 4 pm ET? Alternative suggested times welcome.
Sincerely,
Jamie
||------------------------------------------------------------------------------------------
|| James L. Nagle
|| Professor of Physics, University of Colorado Boulder|| EMAIL: jamie.nagle AT colorado.edu
|| SKYPE: jamie-nagle
|| WEB: http://spot.colorado.edu/~naglej
||------------------------------------------------------------------------------------------
On Sun, Jan 15, 2023 at 12:54 PM Ron Belmont <belmonrj AT gmail.com> wrote:
Hi All,
Since tomorrow is a federal holiday, there will be no sEPD meeting this week. It would be good to follow up via emails to the list, especially about the issues discussed at last week’s meeting, like the status of the electronics and the path forward for further cosmics testing.
Regards,
Ron
-----------------------------------------------------------------------------
Ron Belmont (he/him/his)
RHIC/AGS Users' Executive Committee
Assistant Professor, Department of Physics & Astronomy
University of North Carolina at Greensboro
-----------------------------------------------------------------------------
-
Re: [sphenix-sepd-l] [MINUTES] Re: UPDATE: sEPD meeting Monday 2023-01-09 at 4pm EST
, (continued)
- Re: [sphenix-sepd-l] [MINUTES] Re: UPDATE: sEPD meeting Monday 2023-01-09 at 4pm EST, Rosi Reed, 01/17/2023
- [sphenix-sepd-l] No sEPD meeting this week, Ron Belmont, 01/15/2023
-
Re: [sphenix-sepd-l] No sEPD meeting this week,
Jamie Nagle, 01/15/2023
- Re: [sphenix-sepd-l] No sEPD meeting this week, Ron Belmont, 01/15/2023
-
[sphenix-sepd-l] [URGENT - reply requested] sEPD meeting this week,
Ron Belmont, 01/16/2023
-
Re: [sphenix-sepd-l] [URGENT - reply requested] sEPD meeting this week,
Rosi Reed, 01/16/2023
- Re: [sphenix-sepd-l] [URGENT - reply requested] sEPD meeting this week, Anders Knospe, 01/16/2023
-
Re: [sphenix-sepd-l] [MINUTES] sEPD meeting this week,
Ron Belmont, 01/17/2023
- Re: [sphenix-sepd-l] [MINUTES] sEPD meeting this week, Ejiro Umaka, 01/17/2023
- Re: [sphenix-sepd-l] [MINUTES] sEPD meeting this week, Ron Belmont, 01/20/2023
-
Message not available
- [sphenix-sepd-l] sEPD - follow up short summary (1/21/2023), Jamie Nagle, 01/21/2023
-
Re: [sphenix-sepd-l] [URGENT - reply requested] sEPD meeting this week,
Rosi Reed, 01/16/2023
Archive powered by MHonArc 2.6.24.