Hi All,
We had been discussing what sEPD equipment was going to be installed during the June 21st access.  One idea had been to install half of the North and half of the South.  Discussing the idea with John, he tentatively proposed installing the entire North side instead (and connecting the optical fibers).  The upside is that we'd only have to open one side and put in the diving board on one side.  We'd also have final confirmation that everything fits.  We could also say the north side installation was complete...  Since the MVTX and INTT are on the South side, the North side is the "less busy" option.

We wanted to throw this open to a wider audience to make sure there isn't something that we're missing.  It may be that something comes up in the next 9 days that would prevent this, but barring that does anyone see an issue with this?

Cheers,
Rosi

--
Rosi Reed
RHIC/AGS UEC member
Associate Professor, Physics Department
Lehigh University
(610)758-3907
16 Memorial Drive East Office 406
Bethlehem, PA 18015
she/her/hers


  • [sphenix-sepd-l] sEPD petal installation, Rosi Reed, 06/12/2023

Archive powered by MHonArc 2.6.24.

Top of Page