Skip to Content.
Sympa Menu

sphenix-software-l - [Sphenix-software-l] [minutes] sPHENIX simulation meetings, Tue Dec 8th, 1-3PM EST @ 3-192

sphenix-software-l AT lists.bnl.gov

Subject: sPHENIX discussion of software

List archive

Chronological Thread  
  • From: "Huang, Jin" <jhuang AT bnl.gov>
  • To: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>, "sphenix-software-l AT lists.bnl.gov" <sphenix-software-l AT lists.bnl.gov>
  • Subject: [Sphenix-software-l] [minutes] sPHENIX simulation meetings, Tue Dec 8th, 1-3PM EST @ 3-192
  • Date: Tue, 8 Dec 2015 23:03:35 +0000

Announcement: the next sPHENIX simulation meeting (Dec 15) will be merged into HCal workfest (https://indico.bnl.gov/conferenceDisplay.py?confId=1580 )

 

Also available on agenda page: https://indico.bnl.gov/conferenceDisplay.py?confId=1351

 

 

Several recent pull request: Mike McCumber

 

Recent pull requests:

·       Optimizing evaluation speed:

o   https://github.com/sPHENIX-Collaboration/coresoftware/pull/90

·       Update threshold for tracking modules

o   https://github.com/sPHENIX-Collaboration/coresoftware/pull/91

o   https://github.com/sPHENIX-Collaboration/macros/pull/8

·       For forward Hcal simulation, better handling of missing nodes

o   https://github.com/sPHENIX-Collaboration/coresoftware/pull/93

·       Introduce separate setup macro for four tracking options

o   https://github.com/sPHENIX-Collaboration/macros/pull/7

 

pre-CDR tracking performance check:

·       Working on performance update on tracking in cylinder to establish baseline reference performance.

·       Initial look show concern on simulation with pixel + strip. Purity cross over at pT = 4GeV. Early result appended to the agenda. Still in tuning.

·       Require further work to revise new results for the pre-CDR configuration

·       Talking to Tony to verify.

 

Jin: why does efficiency started with only 60%?

Mike: from dead area:. (92% first layer, 72% 2nd layer, + outer strips dead map)

 

Jin: what caused the shape of vertex residual

Mike: Horn-like shape on Z-vertex residual comes from the fixed vertex location (z = 0cm)  and fixed pitch on strip detector. Will try with smeared vertex which should smear out this shape to a more Guass-like residual

 

 

Database – Chris Pinkenburg

 

Option to support setup based on database or local file. Started with inner Hcal.

Code is already submitted. First use of database need administrative init setup.

Handling is still evolving.

 

Discussions:

·       Will support local cache locally to run outside RCF without database support.

·       Negative run number may be used for standard simulation setup.

·       We should not save the field map, which can get very large. We could save the MD5 or orther ID for the field map in order to reproduce a simulation via DST.

 

Action Item [Chris, Jin]: try it out on Outer Hcal and EMCal too.

 

Hcal update : Abhisek Sen

 

Page 3: timing cut is on the hit level

 

Chris/John L.: the high-side response significantly changed after timing cut too.

John H.: probably due to e/h affected by timing cut.

John L: suggest repeat the terminology used in pre-CDR to quantify the tails.

 

Action Item [Abhisek]: try quantifying the tail after timing cuts

 

Chris: probably better apply the map after PHG4Hit.

Mike: if we apply light correction on the integrated path of PHG4hit, we loss the information for ionization fluctuation.

Abhisek: some hit do have long path (see slide8).

Conclusion: we use G4hit for testing applying light collection map. But we probably want to implement final light map on stepping function.

 

Action Item [Abhisek] : Temp. save local coordinate in G4hit to give a try to figure out the mapping of local coordinate to the light map.

 

Slides 8:

Abhisek: 20% hit goes longer than 2cm in path length in PHG4Hit

John H.: long path length particle probably MIP through scintillator, may not involve large energy deposition.

 

Page 9:

Chris: be careful that at different pseudo-rapidity, radius are corresponding to different path length

 

Chris: where >100ns hit come from?

Action Item [Abhisek]: will look into hit distribution.

 

Jin: Can we verify the timing tail in the test beam data?

John. H. : we can take many more ADC sample in test beam to investigating timing distribution. But usually the amplitude drop to below sensitivity quickly.

 

Prototype simulation: Xiaochun

 

Fixed geometry confliction. Uploaded to GitHub for preview:

https://github.com/phyxch/coresoftware/tree/HcalPrototype2

 

______________________________

 

Jin HUANG

 

Brookhaven National Laboratory

Physics Department, Bldg 510 C

Upton, NY 11973-5000

 

Office: 631-344-5898

Cell:   757-604-9946

______________________________

 

 

> -----Original Message-----

> From: Huang, Jin

> Sent: Monday, December 7, 2015 1:58 PM

> To: 'sphenix-l AT lists.bnl.gov' <sphenix-l AT lists.bnl.gov>; 'sphenix-software-

> l AT lists.bnl.gov' <sphenix-software-l AT lists.bnl.gov>

> Subject: [reminder] sPHENIX simulation meetings, Tue Dec 8th, 1-3PM EST @

> 3-192

>

> Dear All,

>

> This is a reminder for our weekly simulation meeting Tue Dec 8th, 1-3PM EST

> @ 3-192.

>

> Although it is between two collaboration meetings, we will have a brief

> software meeting to update recent progresses. Currently on the agenda,

> Chris will show the use of new sPHENIX database. More contributions are

> welcomed too.

>

> The agenda page is at

> https://indico.bnl.gov/conferenceDisplay.py?confId=1351 , for which the

> common modification password is "1008"

>             For residents at BNL, we will meet in the 3-192 conference room.

>             To join the Meeting via bluejeans: https://bluejeans.com/468481110

>             To join via Phone:

> 1) Dial:

>         +1 408 740 7256

>         +1 888 240 2560(US Toll Free)

>         +1 408 317 9253(Alternate Number)

>         (see all numbers - http://bluejeans.com/numbers)

> 2) Enter Conference ID: 468481110

>

> Cheers,

>

> Jin

>

> ______________________________

>

> Jin HUANG

>

> Brookhaven National Laboratory

> Physics Department, Bldg 510 C

> Upton, NY 11973-5000

>

> Office: 631-344-5898

> Cell:   757-604-9946

> ______________________________



  • [Sphenix-software-l] [minutes] sPHENIX simulation meetings, Tue Dec 8th, 1-3PM EST @ 3-192, Huang, Jin, 12/08/2015

Archive powered by MHonArc 2.6.24.

Top of Page