Dear Takao,
Thanks for the notes.
I would only remark that TPC probably needs to move to BNL around July 2022.
I would only remark that TPC probably needs to move to BNL around July 2022.
It would be nice in a while to see an estimate of how long each sector needs to be exposed to X-rays and then to cosmics to be able to say that it all looks to be operating, and thus to move to testing the next sector.
Regards, Glenn
On Fri, Jul 3, 2020 at 2:56 AM Takao Sakaguchi <takao AT bnl.gov> wrote:
Dear All,
Thanks for those who joined the meeting today. Here are
my fragmented notes from the meeting. We will hold a
follow-up meeting in a month or so.
Best,
Takao
-
[Sphenix-tpc-l] Notes from the TPC signal readout testing plan meeting, Jul 2,
Takao Sakaguchi, 07/03/2020
- Re: [Sphenix-tpc-l] Notes from the TPC signal readout testing plan meeting, Jul 2, Glenn Young, 07/04/2020
Archive powered by MHonArc 2.6.24.