Hi folks,

For the past few weeks a few of us have been meeting Fridays at 2pm to go over the status of the TPC commissioning, lasers, and other issues.  Takao suggested we open up the discussion to the broader group.  Jin has also pointed out the standing TPC operations zoom.  With those in mind, could we try to meet on the TPC operations zoom this afternoon at 2pm to talk status?  That link is https://bnl.zoomgov.com/j/1619343392?pwd=MDExeG91aHgyYlJrUldadjZSaGdhUT09

(If we become a nuisance there, we can fall back to a different zoom link)

The goal is to keep it brief where possible, and it's certainly understood that people may join and continue to work on their task when they're not actively discussing.  
Status of commissioning 
Location of real data files
Diffuse Lasers
Direct Lasers
Alignment 
Calibration software status

As before, feel free to spread the invite to interested parties, or demur if you have other obligations -- I know we're all busy.

-Ross
==========
Dr. Ross Corliss
Research Assistant Professor
Center for Frontiers in Nuclear Science
Stony Brook University
virtual office:  https://stonybrook.zoom.us/my/rossoffice?pwd=ZmZ2SlRIMVFvUUJwbUkyOVNVTmE5QT09



  • [Sphenix-tpc-l] TPC status via zoom, 2pm today?, Ross Corliss, 05/26/2023

Archive powered by MHonArc 2.6.24.

Top of Page