- From: Zhenyu Ye <yezhenyu2003 AT gmail.com>
- To: star-fst-l AT lists.bnl.gov
- Subject: Re: [Star-fst-l] Weekly FST meeting - 8/29/2019
- Date: Thu, 29 Aug 2019 12:53:35 -0500
Meeting minutes
News - Zhenyu
1) Adjustment of milestone timeline
In accordance with module assembly schedule, we will move the completion of
production module assembly by 2 months, and the others by 4 months
2) Hamamatsu Silicon sensors
Received 4+6 prototype sensors from Hamamatsu on Aug 22
Hamamatsu sensor - Zhenyu, Andres
1) Baby sensors
continue measurements with 3 baby sensors. Low leakage current measured from
2 of them over extended period of time (2 weeks). The large leakage current
increase seen with the InnerSensor Chip1 could be due to mis-handing during
the measurement
2) Prototype sensors
By eye, the sensor shapes/sizes seem to match with those of the hybrids. More
detailed inspection will be done under microscope. The IV/CV curves for inner
sensors look reasonable, while those for outer sensors look odd. Will study
by measurements and simulation.
Mechanical structure - Yi, Han-shen
1) Cooling tube
The cooling tube work is now in AIDC’s queue. 8 of them by the end of October
2) Hybrid mounting
Soldering will need to be done at ~200 degree C. Plan to do soldering first
then gluing hybrids onto module structure. Jigs are needed for aligning the
hybrids w.r.t. module structure. Alignment by eye for initial mounting.
3) Module holding frame
Han-shen started working on the drawings
Simulation - Te-Chuan, Krishan
1) GEANT model
Te-chuan is still working on implementing cooling tubes into GEANT
2) tracking study
Krishan discussed results from Daniel’s tracking code and Te-chuan’s detector
simulation.
Action items:
1) Jianing will contact the Nicomatic agent to understand (confirm) the
possible issue with the connectors
2) Jianing will find out the dimensions of the components on T-board so that
Han-Shen can be included into CAD drawings
3) Yi will check the compatibility of T-board and mechanical structure,
seeing if there is a space to accommodate the components on the T-board.
Maybe adding spacers
4) Yi will find out from EASTON and AIDC the tolerance of the module
structure and hybrid mounting
5) Krishan will forward the instruction to run Daniel’s tracking code, and
understand the nHits requirement (true hit or accept any?)
> On Aug 27, 2019, at 1:31 PM, Zhenyu Ye <yezhenyu2003 AT gmail.com> wrote:
>
> Dear all,
>
> We will have a meeting at 9am BNL time tomorrow (Thursday August 29). The
> meeting agenda and bluejeans info can be found at
>
> https://drupal.star.bnl.gov/STAR/blog/yezhenyu/forward-silicon-tracker-weekly-meeting
>
> 1. News - All
> 2. Hamamatsu silicon sensor - Zhenyu Ye
> 3. Mechanical Structure - Yi Yang, Han-sheng Li
> 4. Simulation - Te-Chuan Huang, Krishan Gopal
>
> Best,
> Zhenyu
-
[Star-fst-l] Weekly FST meeting - 8/29/2019,
Zhenyu Ye, 08/27/2019
- Re: [Star-fst-l] Weekly FST meeting - 8/29/2019, Capotosto, Michael, 08/28/2019
-
Re: [Star-fst-l] Weekly FST meeting - 8/29/2019,
Zhenyu Ye, 08/29/2019
- Re: [Star-fst-l] Weekly FST meeting - 8/29/2019, Yi Yang, 08/31/2019
Archive powered by MHonArc 2.6.24.