Mike,

The idea is to assemble 6 V2.1 T-boards, since you have 6 test cables left.

The assembly of them has a relaxed schedule, because of the delay from module
assembly.
I would say the due-date can be as late as this December.

Zhenyu

> On Sep 30, 2019, at 8:29 AM, Capotosto, Michael <capotosto AT bnl.gov> wrote:
>
> Zhenyu,
>
> Did you have a due-date for the completed assembly of the V2.1 T-Boards?
>
> --Mike
>
> -----Original Message-----
> From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> On Behalf Of Ye, Zhenyu
> Sent: Monday, September 16, 2019 10:43 PM
> To: Qian Yang <qianyang_sdu AT sdu.edu.cn>
> Cc: star-fst-l AT lists.bnl.gov
> Subject: Re: [Star-fst-l] Nicomatic connectors
>
> Hi Qian, thanks for the update. Please send 12 female connectors to Michael
> Capotosto at BNL.
>
> Mike, upon receiving these connectors, please inspect them and if they are
> fine, please use them for the new T-board (v2.1), and assemble the T-boards
> with the test cables you have.
>
> Thanks and Best,
> Zhenyu
>
>> On Sep 16, 2019, at 3:26 AM, Qian Yang <qianyang_sdu AT sdu.edu.cn> wrote:
>>
>> Hi All and Zhenyu
>>
>> We received Nicomatic connectors today. The total numbers are 10 male
>> connectors and 16 female connectors.
>> After connected with vendor in China, they told us that they just did an
>> eye inspection and they are not been told about the issue people mentioned
>> before.
>> Yi told me he need at least 8 male connectors. Jianing and I feel more
>> comfortable that we can keep two male and two female connectors at SDU.
>> So, can you tell me the number you need for female connectors? I have send
>> out the box of connectors to Yi this afternoon.
>>
>> A picture of connectors:
>> https://drupal.star.bnl.gov/STAR/system/files/Screen%20Shot%202019-09-16%20at%204.12.06%20PM.png
>>
>> Qian Yang
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l





Archive powered by MHonArc 2.6.24.

Top of Page