star-fst-l AT lists.bnl.gov
Subject: Star-fst-l mailing list
List archive
Re: [Star-fst-l] FST A couple of updates and questions.
- From: Gerard Visser <gvisser AT indiana.edu>
- To: star-fst-l AT lists.bnl.gov
- Subject: Re: [Star-fst-l] FST A couple of updates and questions.
- Date: Wed, 9 Oct 2019 22:53:49 -0400
hi Flemming,
That is correct, 36 inner cables. We will have one cable per silicon module (wedge) assembly, which is 8 APV chips. 3*12 such modules.
There is in the module and inner cable a separate bias "HV" for inner and outer. These will be tied at the patchpanel board, but could be separated later if there was need.
We need 36 patchpanel boards, being 3 assemblies of 12 patchpanel boards, half of IST, which is exactly what we have (other half is lost, it seems).
We need 36 outer cables, and 18 ARM's (we have 36 + spares at IU - a few in test systems), no problem.
We need 6 ARC-II, and all 3 IST readout crates. In principal we could use half as many as you say, but by keeping to 6 we maximize the rate capability / minimize deadtime. The crate now in Prithwish's lab will be *the* spare. (We never had to swap crates or powerboxes in past for FGT/GMT/IST, as far as I recall, but we better keep this spare on hand.)
Hopefully this makes sense... Sincerely,
Gerard
On 10/9/2019 6:14 PM, flemming videbaek wrote:
10/9/2019
A couple of updates and questions.
I am preparing a MS project file for the schedule of the FST. I have taken the information from the review with updates on schedules as presented in misc. presentation later. The implicit time scale for assembly work at FNAL has been included. As the schedule so far is mainly milestones for completion, there will be several open questions that needs to be answered. I plan to send these around to relevant people in the next week or so. The skeleton for this is about 80% done.
The order for the epoxy etc. for the assembly of prototype has been placed in
the BNL system. It will be delivered to BNL and then shipped to FNAL. Three
of 4 items is stock, but one component has an expected 3 week delivery.
Likely ~4 weeks in total from now.
I like to have confirmed that only 36 inner cables are indeed needed. This
implies that for one wedge the HV controls one inner and two outer sensors,
and that we only need to use half of the existing IST ARM/ARC crates. I also
note that the latest drawing from Rahul/John with the cable/cooling routing
does not use the latest layout of the wedges and the cooling. Have BNL gotten
the latest version of CAD model? The routing of the cooling and cables should
be worked on.
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973
phone: 631-344-4106
cell : 631-681-1596
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
[Star-fst-l] FST A couple of updates and questions.,
flemming videbaek, 10/09/2019
- Re: [Star-fst-l] FST A couple of updates and questions., Gerard Visser, 10/09/2019
Archive powered by MHonArc 2.6.24.