hi Zhenyu,
That larger opening is there in the design, see attached screenshot. It is not a vendor mistake.
And, I think that the coverlayer is not to be considered reliable insulation anyway. So the issue (IMHO) is overlap of the epoxy and the other conductors. For sure at the time of the hybrid reviews, I stated that I couldn't speculate how much overflow of
the epoxy there might be, and I asked for the experts on the chip die attachment to review this point.
Anyway, it is what it is, I think the rework plan is probably fine in practice. I am completely confident the tech(s) will remove the copper carefully and check their work. Hopefully they don't have to reject any.
Sincerely,
Gerard
From: Zhenyu Ye <yezhenyu2003 AT gmail.com>
Sent: Wednesday, February 10, 2021 11:14 AM
To: Visser, Gerard <gvisser AT indiana.edu>
Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: Re: [Star-fst-l] FST slides from Monday
Sent: Wednesday, February 10, 2021 11:14 AM
To: Visser, Gerard <gvisser AT indiana.edu>
Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: Re: [Star-fst-l] FST slides from Monday
Hi Gerard,
I must have a bad memory, because I don’t remember this request. Review of the design of the hybrid or of any of the detector is not their responsibility. Even if one reviews the layout, one would not find this because by design the GND copper should be covered by insulation layer, but the vendor opened a larger window so that parts of the GND is exposed.
Zhenyu
> On Feb 10, 2021, at 9:34 AM, Visser, Gerard <gvisser AT indiana.edu> wrote:
>
> hi Xu, Flemming,
> Interesting.
> I feel I must point out, I asked (several times) that we should ask Fermilab Sidet people to review the hybrid layout files, specifically because these other copper areas in the layout looked to me too close to the die attach pad. I believe I was told that the layout was examined and it was fine. Clearly, that's not the case. Oh well.
> Reworking every hybrid in this manner is not zero risk.
>
> Gerard
>
> p.s. On slide 6 - extra noise in cooling test - the cooling tube was I hope grounded to T-board according to plan. Right? (If not, there is risk of permanent damage, not only of higher noise.)
>
>
> From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> on behalf of videbaek <videbaek AT bnl.gov>
> Sent: Wednesday, February 10, 2021 9:15 AM
> To: Star-fst L <star-fst-l AT lists.bnl.gov>
> Subject: [Star-fst-l] FST slides from Monday
>
> Hi Xu,
>
> Are your slides from Monday's meeting available? I do not see them on
> the meeting page.
>
> best Flemming
>
>
> --
> Flemming Videbaek
> senior scientist
> videbaek @ bnl.gov
> Brookhaven National Lab
> Physics Department
> Bldg 510D
> Upton, NY 11973
>
> phone: 631-344-4106
> cell : 631-681-1596
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
I must have a bad memory, because I don’t remember this request. Review of the design of the hybrid or of any of the detector is not their responsibility. Even if one reviews the layout, one would not find this because by design the GND copper should be covered by insulation layer, but the vendor opened a larger window so that parts of the GND is exposed.
Zhenyu
> On Feb 10, 2021, at 9:34 AM, Visser, Gerard <gvisser AT indiana.edu> wrote:
>
> hi Xu, Flemming,
> Interesting.
> I feel I must point out, I asked (several times) that we should ask Fermilab Sidet people to review the hybrid layout files, specifically because these other copper areas in the layout looked to me too close to the die attach pad. I believe I was told that the layout was examined and it was fine. Clearly, that's not the case. Oh well.
> Reworking every hybrid in this manner is not zero risk.
>
> Gerard
>
> p.s. On slide 6 - extra noise in cooling test - the cooling tube was I hope grounded to T-board according to plan. Right? (If not, there is risk of permanent damage, not only of higher noise.)
>
>
> From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> on behalf of videbaek <videbaek AT bnl.gov>
> Sent: Wednesday, February 10, 2021 9:15 AM
> To: Star-fst L <star-fst-l AT lists.bnl.gov>
> Subject: [Star-fst-l] FST slides from Monday
>
> Hi Xu,
>
> Are your slides from Monday's meeting available? I do not see them on
> the meeting page.
>
> best Flemming
>
>
> --
> Flemming Videbaek
> senior scientist
> videbaek @ bnl.gov
> Brookhaven National Lab
> Physics Department
> Bldg 510D
> Upton, NY 11973
>
> phone: 631-344-4106
> cell : 631-681-1596
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
Attachment:
Untitled.png
Description: Untitled.png
-
[Star-fst-l] FST slides from Monday,
videbaek, 02/10/2021
- Re: [Star-fst-l] FST slides from Monday, Xu Sun, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Visser, Gerard, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Visser, Gerard, 02/10/2021
- Re: [Star-fst-l] FST slides from Monday, Xu Sun, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Zhenyu Ye, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Visser, Gerard, 02/10/2021
- Re: [Star-fst-l] FST slides from Monday, Zhenyu Ye, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Visser, Gerard, 02/10/2021
- Re: [Star-fst-l] FST slides from Monday, videbaek, 02/10/2021
-
Re: [Star-fst-l] FST slides from Monday,
Visser, Gerard, 02/10/2021
Archive powered by MHonArc 2.6.24.