Hello,

as we discussed, I plan to use a 2nd DAQ PC to be able
to sustain the maximum rate.

Apart from the physical move of the fibers it will
also entail a CVS-update and DAQ Reader code
refresh for any software. Note that you won't need
to change your code at all. I also need a bit of Jeff's
time to set Run Control up.

Because it is invasive I would like to plan for
~2-3 days of FST downtime when you won't
be able to run any tests with Run Control
but I would like to have the ARCs powered up
(I don't need APVs or HV). NB, they seem to be off
most of the time.

Would next Monday, Oct 4, be OK for this?

-- Tonko