Re: [Star-hp-l] Run23 data taking plan from HP-pwg
- From: Nihar Sahoo <nihar AT rcf.rhic.bnl.gov>
- To: James Dunlop <dunlop AT bnl.gov>
- Cc: STAR HardProbes PWG <star-hp-l AT lists.bnl.gov>
- Subject: Re: [Star-hp-l] Run23 data taking plan from HP-pwg
- Date: Sat, 01 Apr 2023 18:17:25 +0530
Dear James and Ahmend,
Thank you for your input and comments.
Please find my replies inline.
On 2023-04-01 05:05, James Dunlop wrote:
Ahmed, Nihar,Thank you for pointing this. I was thinking on this direction either we should increase or lower (BHT3 is 5.76 and 3x3 patch 7.44 thresholds) for L2gmma trigger thresholds.
The real question is what threshold you need.
BHT1, 2, 3 is just 3 different thresholds in Et for a single High
Tower,
which you can choose/negotiate with other PWG's. e.g. Upsilon
tends to want a specific Et cut to avoid cutting too hard into the
invariant
mass distribution beyond, say, 9 GeV in M (and so 4.5 GeV in Et, try
to keep it more like 4 so
you can understand the combinatoric background),
and UPC J/Psi wants their Et cut very low.
As we use 6 GeV cutoff to high tower trigger energy for our offline anlysis, probably it might be Ok to keep the above thresholds for Run23. and could that be decided during run time if it is needed?
But I welcome your suggestion and we can further discuss at trigger board meeting.
L2 is somewhat useful to moderate a strict high tower
into something that incorporates information from other
towers, but it can be problematic in the high Underlying Event
condition of Au+Au collisions.
--J
On Mar 31, 2023, at 6:45 PM, Ahmed M. Hamed via Star-hp-l
<star-hp-l AT lists.bnl.gov> wrote:
Dear Nihar;
Thanks a lot for the slides.
Two comments and one question:
1) I don't understand why not L2gamma and not BHT3+L2gamma; I really
don't know what BHT3 adds to the trigger components?
As James mentioned BHT1,2,3 are different threshold used during Run14 and 16.
"BHT3+L2gamma" label used for above last runs with high tower threshold is 5.76 GeV and 3x3 patch threshold is 7.44 GeV. Again as James pointed out We may need to think on these thresholds for Run23 (and also Run25 very high lumi) which depend upon the low and high lumi.
I will discuss this topic at trigger borad meeting to come up with these thresholds (either we can set these numbers now or during the run time, I need suggestion in this direction)
I quickly calculated the following numbers from Run14 runlog the triggered event fractions (L2gamma trigger events/MB events)2) I think what you need to quote here (slide # 6) are the numbers
of events as a percentage from the number of triggered events per
luminosity, and not all events.
~0.006 for high
~0.002 for low
As L2gamma trigger events will be very small is size even for upcoming runs. we may ask for Mudst production only. But picodst production is also possible and both energy and adc information are there inside pico.Question: Migrating from the mudst to picodst what information has
been thrown away? e.g. Whether running the cluster algorithm (BSMD)
for the transverse shower profile over the picodst is still an
option; or one must run over the mudst files in order to find all
information required by the cluster algo.; i.e. the energy and adc
per strip.
Thank you
Nihar
Best Regards
On Fri, Mar 31, 2023 at 2:23 PM Nihar Sahoo via Star-hp-l
<star-hp-l AT lists.bnl.gov> wrote:
Hello All,https://drupal.star.bnl.gov/STAR/blog/nihar/HP-pwg-Run23-discussion
The proposed triggers for gamma+jet and HF physics have been
updated as
Rongrong suggested.
(Slide#4)
https://drupal.star.bnl.gov/STAR/blog/nihar/HP-pwg-Run23-discussion
Thank you
Nihar
On 2023-03-31 12:17, Ma, Rongrong wrote:
Hello Niharpropose:
Thanks for the slides. I think it will be nice if we can list
explicitly the triggers we want.
In terms of quarkonium physics, here are the triggers we
Nihar
* dimuon+zdc_coin+vpd100
* BHT2+zdc_coin+vpd100
* BHT1+zdc_coin+vpd10
* monitor triggers: vpd-zdc-novtx, vpd-zdc-10
Best
Rongrong
-------------------------
From: Star-hp-l <star-hp-l-bounces AT lists.bnl.gov> on behalf of
Sahoo via Star-hp-l <star-hp-l AT lists.bnl.gov>vertex
Sent: Thursday, March 30, 2023 12:45 AM
To: Star-hp L <Star-hp-l AT lists.bnl.gov>
Subject: [Star-hp-l] Run23 data taking plan from HP-pwg
Hello HP-pwg members,
We were asked to provide inputs, particularly on trigger setup,
seen
selection, and BSMD usage, for Run23 data taking. You must have
Rongrong's emails in this direction.be
A few slides that we have prepared our response (questions can
found
inside).
_______________________________________________measurements
Mainly we have included STAR gamma+jet and also dimuon
requirement in these slides if you want to propose/suggest anyplease let
specific
trigger/detector usage for RUn23 relevant to your analysis,
_______________________________________________
us know asap.
Coming Monday we plan to present at the trigger board meeting.
Thank you
Nihar for HP-conveners
_______________________________________________
Star-hp-l mailing list
Star-hp-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-hp-l
Star-hp-l mailing list
Star-hp-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-hp-l
Star-hp-l mailing list
Star-hp-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-hp-l
--
He/Him/His
Please do not feel obligated to respond to this message outside of
your work hours.
James C Dunlop Ph.: (631) 344-7781
Building 510A Cell: (631)316-8153
P.O. Box 5000
Brookhaven National Laboratory
Upton, NY 11973
dunlop AT bnl.gov
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Nihar Sahoo, 04/01/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Ahmed M. Hamed, 04/01/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Nihar Sahoo, 04/02/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Rosi Reed, 04/02/2023
- Re: [Star-hp-l] Run23 data taking plan from HP-pwg, Rosi Reed, 04/02/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Ahmed M. Hamed, 04/02/2023
- Re: [Star-hp-l] Run23 data taking plan from HP-pwg, Rosi Reed, 04/02/2023
- Re: [Star-hp-l] Run23 data taking plan from HP-pwg, Jacobs, William W, 04/02/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Rosi Reed, 04/02/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Nihar Sahoo, 04/02/2023
-
Re: [Star-hp-l] Run23 data taking plan from HP-pwg,
Ahmed M. Hamed, 04/01/2023
Archive powered by MHonArc 2.6.24.